January 29, 2026 - March 15, 2026 (45 days) Closed
Last updated
This decision is for a new Environmental Compliance Approval (sewage) for the replacement and upgrading of existing onsite sewage works at the A.W. Campbell Conservation Area, located at 8477 Shiloh Line, Middlesex County, Ontario.
Instrument type:
New - Approval for a consent (subject to conditions) in an area where there is no official plan in place
ERO number
025-1369
Notice type
Instrument
Notice stage
Decision
Decision posted
Proposal posted
Comment period
January 29, 2026 - February 28, 2026 (30 days) Closed
Last updated
Pursuant to Section 53 of the Planning Act, provisional consent was granted on March 24, 2026 in respect of Application 58-C-252597 for a lot addition in the unincorporated Township of Stirling, District of Thunder Bay. The last day this decision can be appealed is April 13, 2026.
January 27, 2026 - March 13, 2026 (45 days) Closed
Last updated
Certificate of Property Use No. 7166-DJ2J34 was issued to 351 Margaret Limited and 351 Margaret Limited Partnership for the intended mixed commercial, community, residential and institutional use of the property at 351 Margaret Avenue, City of Kitchener Ontario.
February 4, 2026 - March 21, 2026 (45 days) Closed
Last updated
This proposal is to amend the Environmental Compliance Approval with Limited Operational Flexibility (air) No. 1708-7K7LLC which replaces all the current Environmental Compliance Approvals for Air at this facility and will include the addition of new or historically unapproved sources for all emissions from Project Nikolas Company Inc.
December 27, 2024 - February 10, 2025 (45 days) Closed
Last updated
A new Environmental Compliance Approval was issued to First Ardelt Holdings Limited, for approval of the establishment of stormwater management works to service a catchment area of approximately 2.7 hectares, discharging to the existing 825 millimetres diameter storm sewer located along Ardelt Place and ultimately to Schneider Creek.
January 9, 2025 - February 23, 2025 (45 days) Closed
Last updated
An amended Environmental Compliance Approval was issued to C.H. Demill Holdings Inc. for approval of existing works for dewatering of the extraction areas of the Long’s Quarry and the immediately adjacent to east Melrose Quarry located in proximity of the southern Long's Quarry site boundary.
August 16, 2024 - September 30, 2024 (45 days) Closed
Last updated
A new Environmental Compliance Approval was issued to Tristone Aggregates Inc. for approval of upgrades to the existing works for the collection, transmission, treatment and reuse of wash water from aggregate washing operations located within the existing Cartwright Pit located at 40581 Winthrop Road, Londesborough, Municipality of Central Huron.
September 9, 2024 - October 24, 2024 (45 days) Closed
Last updated
The ministry has amended existing Environmental Compliance Approval (ECA) No. 3-0386-78-006 to incorporate a change in the owner name, reflect current site use, and permit the establishment of additional stormwater management works to serve the Wessuc Inc. site at 1693 Colborne St. E. in Brantford, Ontario.
An amendment to the existing approval has been issued to TEVA Canada Limited. This approval is for the renewal of the Limited Operational Flexibility for an Environmental Compliance Approval (air & noise) No. 6186-A26P7S for TEVA Canada Limited (TEVA), a pharmaceutical manufacturing facility located in Whitfield-Stouffville, Ontario.
December 12, 2025 - January 11, 2026 (30 days) Closed
Last updated
The Director of Exploration has made a decision on the exploration permit application PR-25-000265 to Stirling Metals Corp. for early exploration activities.
The decision is to issue the mineral exploration permit.
November 26, 2025 - January 10, 2026 (45 days) Closed
Last updated
Approval is granted to amend the existing Environmental Compliance Approval (waste disposal site) No. A-500-1188155825 for a processing facility in the City of Welland, Ontario.
This proposal is to amend the Environmental Compliance Approval No. 3257-CRAPT7 for the stormwater management works serving the Vine Fresh Acres Ltd. Phase 3 Greenhouse Expansion Site, located at 420 Essex Road 14, and the existing Lebo Farms Ltd. greenhouse site located at 429 Mersea Road 8, both in the Municipality of Leamington.
The ministry has issued a new Environmental Compliance Approval (Sewage) to Enbridge Gas Inc. for modifications to existing stormwater management works servicing the Dawn Natural Gas Facility with associated buildings and structures, drive aisles, parking, and gravel areas located at 3332 Bentpath Line, Dawn-Euphemia Township, County of Lambton.