In principle, OWMA supports…

ERO number

019-4219

Comment ID

59220

Commenting on behalf of

Ontario Waste Management Association (OWMA)

Comment status

Comment approved More about comment statuses

Comment

In principle, OWMA supports the approach to allow some projects to follow a streamlined approval process with only designated projects subject to comprehensive environmental assessments. We recommend the following changes to waste project thresholds

• Under section 23 & 25, a comprehensive EA should be required for landfill projects that increase the total waste disposal volume by more than 375,000 cubic metres, or 25% if the change would increase the total waste disposal volume by more than 375,000 cubic metres.

Applying a 25% volume increase threshold for volume increases above 375,000 cubic metres is more reasonable and would allow more of Ontario’s larger public and private landfill sites (that currently manage about 70% of Ontario’s waste disposal) to follow a streamlined process for adding necessary waste capacity and aid in Ontario’s economic recovery. Environmental safeguards would be in place since these sites have already been subject to a comprehensive environmental assessment in their establishment. Our detailed comments are in the enclosed supporting document letter.