Decision summary
Approval was granted for a site plan amendment to Lafarge Canada Inc. to amend the current site plan to allow additional extraction to occur below the groundwater table.
Location details
Site location details
43.05939 degrees North x 81.20730 degrees West, London, Middlesex County.
Part Lot 5, Concession 5, Geographic Township of London.
The site is located approximately 2 kilometres northeast of Fanshawe.
The site is ARA licence No. 2081.
The site is adjacent to the east boundary of ARA licence No. 2190.
A link to our mapping tool allows you to locate and view licensed sites under the ARA.
Site location map
The location pin reflects the approximate area where environmental activity is taking place.
View this location on a map opens link in a new windowProponent(s)
Lafarge Canada Inc.
6509 Airport Road
Mississauga,
ON
L4V 1S7
Canada
Decision details
The changes to the site plan for ARA Licence No. 2081 were approved by the Director on November 24, 2025.
The approval allows Lafarge Canada Inc. to amend the current site plan to change the final depth of extraction from above the water table to below the water table to a maximum depth of 258 masl., in a site that allows excavation below the water table in another area of the site.
A copy of the approved site plan for this licenced site can be obtained from the Contact identified below.
Effects of consultation
One (1) comment was received in response to the Environmental Registry notice.
The comment requested the licensee to conduct an Environmental Impact Assessment (EIA) and had concerns over groundwater quality, ecosystem preservation and biodiversity. A request for comprehensive monitoring and compliance on the site.
Comments were received through the Aggregate Resources Act (ARA) consultation process.
The concerns were related to:
- Well head protection zone, groundwater map, temperature profiles and update radius of influence calculations.
- Notes added to site plan referencing the groundwater monitoring program and a note added to the rehabilitation plan discussing well abandonment once they are no longer needed.
- Removal of ambiguous language such as +-.
- Additions to the site plan for existing and proposed buildings, processing equipment,
- Location, footprint and vegetation of berms on site.
- Tree screen details, including species, monitoring and maintenance.
- Excess soils conditions added to site plan.
- Add land uses such as zoning to site plan.
- Add direction for phasing on site plan.
- Clarification on recycling, number of lifts and fuel storage,
The concerns were addressed by providing additional information and revisions to the site plan.
Supporting materials
View materials in person
Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.
Get in touch with the office listed below to find out if materials are available.
300 Water Street
ARAApprovals@ontario.ca
Peterborough,
ON
K9J 3C7
Canada
How to Appeal
Appeals are not allowed
This instrument type cannot be appealed. Learn more about our consultation process.
Connect with us
Contact
ARA Contact
300 Water Street
ARAApprovals@ontario.ca
Peterborough,
ON
K9J 3C7
Canada
Original proposal
Proposal details
Proposal Updates
This notice was updated on August 14, 2025, to advise the public that there has been no change to the status of the proposal, and it is still being considered. No additional opportunity for comment is being provided for at this time.
This notice was initially published on August 29, 2023 with a comment period of 30 days. It has been extended on September 13, 2023 to October 30th, 2023 for a total of 62 days.
Proposal Details
Application has been made by Lafarge Canada Inc. to amend the current site plan to change the final depth of extraction from above the water table to below the water table to a maximum depth of 258 masl, in a site that allows excavation below the water table in another area of the site.
Public consultation opportunities
The proposed request for this licence is being circulated within the Ministry of Natural Resources and Forestry. Additionally, notification of this application has been forwarded to the City of London, Ministry of the Environment, Conservation and Parks– Species at Risk, Ministry of the Environment, Conservation and Parks – London Office, Upper Thames River Conservation Authority and Landowners within 120 metres of the boundary of the pit, for comment.
Supporting materials
View materials in person
Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.
Get in touch with the office listed below to find out if materials are available.
300 Water Street
ARAApprovals@ontario.ca
Peterborough,
ON
K9J 3C7
Canada
Comment
Commenting is now closed.
This consultation was open from August 29, 2023
to October 30, 2023
Connect with us
Contact
Shane Stuart
4th Floor S, 300 Water Street
Peterborough,
ON
K9J 3C7
Canada
Comments received
Through the registry
1By email
0By mail
0