Permit to Take Water No. 5415-DG2MK6 has been issued to Tralee Development Inc. renewing PTTW No. 0382-C2WKRX for construction dewatering purposes. Water will be taken from one well, located in the City of Richmond Hill, Ontario.
December 20, 2024 - January 19, 2025 (30 days) Closed
Last updated
The Permit to Take Water No. P-300-8310890223 (V1.0) was issued to Non-profit Retirement Residences of Elliot Lake Inc. on May 5, 2025, to renew the Permit No. 4164-B9QP8P. Water will be taken from Ryan Lake for the purpose of golf course irrigation, located in the City of Elliot Lake, District of Algoma, Ontario.
Permit to Take Water No. 6815-DG7NLJ has been issued to Earlglen Investments Inc. renewing Permit to Take Water No. 8221-CWPNDX for construction dewatering purposes. Water will be taken from six wells related to construction activities, located in the City of Richmond Hill, Ontario.
January 27, 2025 - February 26, 2025 (30 days) Closed
Last updated
The Permit to Take Water No. 7734-DG6GTZ was issued to G. Tackaberry & Sons Construction Company Limited on May 01, 2025, for renewal of PTTW No. 3048-9VEKRN. Water will be taken from one pond for pits and quarry operations, located in the Township of Elizabethtown-Kitley, Ontario, for 10 years.
Permit to Take Water No. P-300-7332320219 has been issued to Fouro Towers Builders Ltd. for construction dewatering purposes. Water will be taken from one well located in Markham, Ontario
The Permit to Take Water No. 0631-DG2NZF was issued to Badgeley Island Aggregates Inc. on May 1, 2025, to renew the Permit No. 8624-9LKJLT. Water will be taken from two ponds for quarry dewatering purposes, in the Municipality of Killarney, District of Sudbury, Ontario.
January 7, 2025 - February 6, 2025 (30 days) Closed
Last updated
Permit to Take Water No. 6417-DEAMLV has been issued to Summerlea Golf Club Ltd. for golf course irrigation purposes. Water will be taken from two wells in Whitby, Ontario.
January 21, 2025 - February 20, 2025 (30 days) Closed
Last updated
The Permit to Take Water No. 4356-DFZKNL was issued to Bedard Sand & Gravel Limited on April 24, 2025, for renewal of Permit to Take Water No. 0886-9V6KEN. Water will be taken from one pond, for aggregate washing purposes in Woodville, Ontario for 10 years.
The Permit to Take Water No. 7511-DFRHU2 was issued to Waste Management of Canada Corporation on April 24, 2025, for renewal and consolidation of PTTW No. 0204-9UCSW6 & 5547-9UCQ26. Water will be taken from two wells and four ponds for purposes of on-site landfill, located in the City of Ottawa, Ontario for 10 years.
January 27, 2025 - February 26, 2025 (30 days) Closed
Last updated
Permit to Take Water No. P-300-1033051430 version 1.0 has been issued to Anatolia Real Estate Corp. for construction dewatering purposes. Water will be taken from four wells located in the Town of Milton, Ontario.
November 20, 2024 - December 20, 2024 (30 days) Closed
Last updated
The Permit to Take Water No. P-300-1314662572 (version 1.0) was issued to 12714001 Canada Inc. on April 23, 2025. Water will be taken from two ponds for construction dewatering purposes at 2983 Navan Road in Ottawa, Ontario for five years.
January 28, 2025 - February 27, 2025 (30 days) Closed
Last updated
New Permit to Take Water No. P-300-5327850891 V1.0 has been issued to Brixen Developments Inc. foundation drainage purposes. Water will be taken from one well for located in the City of Toronto, Ontario for 10 years.
January 9, 2025 - February 8, 2025 (30 days) Closed
Last updated
The Permit to Take Water No. 5671-DFRLTS was issued to Lafarge Canada Inc. on April 17, 2025, for renewal of 201-9UWQHE. Water will be taken from one pond for quarry and pit dewatering, aggregate washing and dust suppression purposes, located in the City of Ottawa, Ontario, for 10 years.
January 23, 2025 - February 22, 2025 (30 days) Closed
Last updated
The Permit to Take Water No. P-300-9324804731 (version 1.0) was issued to Larga Baffin Ltd. on April 16, 2025. Water will be taken from one pond for construction dewatering purposes, located in the City of Ottawa, Ontario, for three years.
December 24, 2024 - January 23, 2025 (30 days) Closed
Last updated
Permit to Take Water No. P-300-1323326638 was issued to African Lion Safari & Game Farm Ltd. on April 8, 2025. Water will be taken from one well for wildlife park water supply purposes, located in the City of Hamilton, Ontario.
December 27, 2024 - January 26, 2025 (30 days) Closed
Last updated
Permit to Take Water No. 8488-DEVH8D was issued to Waterford Sand & Gravel Limited on April 14, 2025. Water will be taken from two ponds for pits & quarry dewatering and industrial manufacturing purposes, located in the Township of Dunnville, Ontario.
January 27, 2025 - February 26, 2025 (30 days) Closed
Last updated
Permit to Take Water No. 5636-DEVN8C was issued to Dundas Valley Golf and Curling Club on April 14, 2025. Water will be taken from one well and one pond for golf course irrigation purposes, located in the Town of Dundas, Ontario.
January 21, 2025 - February 20, 2025 (30 days) Closed
Last updated
Permit to Take Water No. P-300-3327860800 was issued to Pineland Gardens Limited on April 16, 2025. Water will be taken from one pond and one well for golf course irrigation purposes, located in the City of Hamilton, Ontario.
December 19, 2024 - January 18, 2025 (30 days) Closed
Last updated
The Permit to Take Water No. 8354-DFRK82 was issued to G. Tackaberry & Sons Construction Company Limited on April 16, 2025, for renewal of PTTW No. 3133-9VMPJ8. Water will be taken from one pond for quarry operations, aggregate washing, construction and dust control purposes at the Wilson Quarry, located in Montague, Ontario, for 10 years.