Suncor Energy Inc. - Certificate of property use

Instrument type: Certificate of property use

ERO number
019-2040
Ministry reference number
7232-BPZQMQ
Notice type
Instrument
Act
Environmental Protection Act, R.S.O. 1990
Posted by
Ministry of the Environment, Conservation and Parks
Notice stage
Decision
Decision posted
Comment period
July 6, 2020 - August 20, 2020 (45 days) Closed
Last updated

This consultation was open from:
July 6, 2020
to August 20, 2020

Decision summary

A Certificate of Property Use was issued to Suncor Energy Inc. and Suncor Energy Products Partnership for the property located at 288 and 290 Woolwich Street, Guelph, Ontario.

Location details

Site address

288 and 290 Woolwich Streeet
Guelph, ON
Canada

Site location details

288 and 290 Woolwich Street, Guelph

With a Legal Description of:

Lots 60, 74 & 75, Registered Plan 35, City of Guelph

Being all of PIN: 71292-0177 (LT)

Site location map

The location pin reflects the approximate area where environmental activity is taking place.

View this location on a map opens link in a new window

Proponent(s)

Suncor Energy Inc.
3275 Rebecca Street
Oakville, ON
L6L 6N5
Canada

Suncor Energy Products Partnership
2489 North Sheridan Way
Mississauga, ON
L5K 1A8
Canada

Decision details

Certificate of Property Use (CPU) No. 7232-BPZQMQ was issued to Suncor Energy Inc. on September 1, 2020 for the intended future Residential Use of the Property.

The CPU requires the instrument holder to ensure that the following key measures are undertaken:

  • installing, inspecting and maintaining hard cap and fill cap barriers on the property as per Sections 4.2(a) and 4.2(e) of the CPU
  • prohibiting the construction of any new building (s) on the property unless the new building(s) is constructed as specified in Section 4.2 (f) of the CPU
  • implementing a soil and groundwater management plan during any intrusive activities undertaken on the property potentially in contact with COCs in soil and groundwater that have been identified in the RA at concentrations that exceed the Applicable Site Condition standards as per Section 4.2 (p) of the CPU
  • implementing a health and safety plan during any intrusive activities undertaken on the property potentially in contact with COCs in soil and groundwater that have been identified in the RA at concentrations that exceed the applicable site condition standards as specified in Section 4.2 (q) of the CPU
  • implementing a groundwater monitoring program as specified in Section 4.2 (r) of the CPU
  • prohibiting the planting of fruit and vegetables for consumption, other than those planted in above ground containers such that they are isolated from the subsurface conditions as per Section 4.3 of the CPU
  • prohibiting the use of groundwater in on or under the Property as per Section 4.4 of the CPU
  • registering a certificate on the property title in accordance with Section 197 of the Environmental Protection Act and that before dealing with the property in any way, a copy of the CPU is to be given to any person who will acquire an interest in the property as per Section 4.7, 4.8 and 4.9 of the CPU

No changes were made to the draft CPU prior to it being finalized by the director. A copy of the issued CPU has been attached to this notice.

Comments received

Through the registry

1

By email

1

By mail

0
View comments submitted through the registry

Effects of consultation

One (1) electronic comment was received through the ERO with respect to ERO 019-2040 (ministry reference 7232-BPZQMQ) from a member of the public. A member of the public also contacted the Guelph District Office directly through email and telephone on several occasions regarding historical on and off-site contamination related to this site. These questions were answered directly by Ministry of the Environment, Conservation and Park’s (ministry) staff.

All questions and comments received regarding this proposal were considered by the director and the following additional general information has been provided:

The property located at 288 and 290 Woolwich Street, Guelph (the property) was a former automotive station and retail fuel outlet which was decommissioned in the early 1990’s and has remained vacant ever since.

The property is bounded by two residential properties to the west and municipal roadways to the north (London Road West), east (Woolwich Street) and south (Edwin Street).

The property is currently owned by Suncor Energy Inc. (Suncor) and ongoing environmental investigations have been completed since the early 1990’s with remedial excavations being undertaken in 2012 and 2013. 

Based upon the information provided, Suncor intends to file a Record of Site Condition in accordance with Ontario Regulation 153/04 (as amended) for the intended future residential use of the property. The Record of Site Condition process is a proponent driven process and is only applicable to the property for which the Record of Site Condition is filed. In order to obtain a Record of Site Condition for this property, Suncor has chosen to undertake a risk assessment to address any remaining contaminants of concern that have been identified.

Risk assessments are an option to property owners under Ontario Regulation 153/04 (as amended) and scientifically examines the potential risks posed to humans, plants, wildlife and the natural environment for the contaminants of concern for all identified pathways on the risk assessment property.

Through the risk assessment process, property specific standards are generated that are protective of human health and the environment for the intended future use of the property and must also demonstrate that the current site conditions do not pose unacceptable risks off-site. Within the risk assessment, the qualified person evaluates the potential risks to human health and the environment and identify any risk management measures that may be required to be implemented on the property in relation to it’s intended future use. These risk management measures are incorporated into a Certificate of Property Use which is only applicable to the former Suncor property and is binding on the current property owner along with any future property owner.

The specific questions within the electronic ERO submission were considered and are addressed as follows:

1. In posting this notice, it seems like the Guelph Office (GO) has concluded that the data provided by Suncor is satisfactory, including that it demonstrates no offsite contamination. However, the GO has not been provided with any data from the adjacent properties - so I ask, how can this conclusion be made?

The risk assessment for this property was received by the ministry and reviewed by several different technical groups, all who provide their own property specific risk-based comments, perspectives and recommendations as may be required. As part of the review process for the risk assessment, the local district office engineer reviewed the information provided within the risk assessment along with all available historical information on file with the ministry. This information was used to evaluate the property itself and any potential off-property issues that may exist before and after redevelopment.

After reviewing the initial risk assessment, the local district office specifically requested that Suncor’s consultant complete an evaluation of the potential risk to the residential properties that abut the western property boundary. As a result of this additional evaluation, taking into consideration the historical information on file, no adverse effects are anticipated off-site. Despite this, a confirmatory groundwater monitoring program, that includes a contingency plan and the installation of an additional well along the western property boundary, was incorporated into the proposed Certificate of Property Use along the western property boundary. The results of the groundwater monitoring program will be reviewed by the ministry on an annual basis to determine if any additional action in the area is warranted.

As noted above, the conclusions of the risk assessment and requirements of the ministry’s Certificate of Property Use only apply to the former Suncor property.

2. Can I plant vegetables? Would you? Can i eat from the mulberry tree near the property line? Would you?

With respect to the ingestion of garden produce/fruit on the former Suncor property, this was evaluated in the risk assessment and it was concluded that no risks to human health were anticipated through the ingestion of home-grown garden produce/fruit. That being said, the consultant opted to include a risk management measure in the Risk Management Plan to prohibit vegetables/fruit from being planted on that property in the future as an additional control measure. This is a typical risk management measure that is included by consultants in many brownfields being redeveloped into residential properties.

As noted above, the conclusions of the risk assessment and requirements of the ministry’s Certificate of Property Use only apply to the former Suncor property.

3. Should I go into my basement when the CPU conditions will stipulate that the next build on that site would not be allowed to have below grade dwelling? Can my children?

The risk assessment evaluated the potential for vapour intrusion into a typical residential building, that includes a typical residential basement on the former Suncor property. The conclusion was that no unacceptable risks were identified. As a result, no risk management measures are required for typical residential buildings with basements.

Risk management measures for vapour intrusion were included in the proposed Certificate of Property Use for potential future residential buildings that may be constructed with more than one sub-grade level (i.e. multiple levels of underground parking or multiple sub-grade levels) on the former Suncor Property.

As requested by the local district office, Suncor’s consultant completed an evaluation of the potential risk to the residential properties that abut the western property boundary. As a result of this additional evaluation along with the information the ministry has reviewed to date, no adverse effects are anticipated off-site. Despite this a confirmatory groundwater monitoring program, that includes a contingency plan, was incorporated into the proposed Certificate of Property Use along the western property boundary. The results of the groundwater monitoring program will be reviewed by the ministry on an annual basis to determine if any additional action in the area is warranted and is to be implemented upon the issuance of the Certificate of Property Use.

As noted above, the conclusions of the risk assessment and requirements of the ministry’s Certificate of Property Use only apply to the former Suncor property.

After considering all of the above, no changes were made to the proposed Certificate of Property Use by the Director prior to it being finalized.

Supporting materials

View materials in person

Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.

Get in touch with the office listed below to find out if materials are available.

How to Appeal

This instrument decision can be appealed. You have 15 days from September 9, 2020 to begin the appeal process.

Carefully review the information below to learn more about the appeal process.

How to appealClick to Expand Accordion

For instrument decisions published on or after June 1, 2021, please refer to the updated instructions for information on how to appeal a decision.

Appeal process for decisions published before June 1, 2021

If you’re an Ontario resident, you can start the process to appeal this instrument decision.

First, you’ll need to seek leave (i.e. get permission) from the relevant appellate body to appeal the decision.

If the appellate body grants leave, the appeal itself will follow.

Seek leave to appeal

To seek leave to appeal, you need to do these three things:

  1. prepare your application
  2. provide notice to the minister
  3. mail your application to three parties

1. Prepare your application

You’ll need to prepare an application. You may wish to include the following things in your application:

  1. A document that includes:
    • your name, phone number, fax number (if any), and/or email address
    • the ERO number and ministry reference number (located on this page)
    • a statement about whether you are a resident in Ontario
    • your interest in the decision, and any facts you want taken into account in deciding whether you have an interest in the decision
    • the parts of the instrument that you’re challenging
    • whether the decision could result in significant harm to the environment
    • the reason(s) why you believe that no reasonable person – having regard to the relevant law and to any government policies developed to guide decisions of that kind – could have made the decision
    • the grounds (facts) you’ll be using to appeal
    • the outcome you’d like to see
  2. A copy of the instrument (approval, permit, order) that you you are seeking leave to appeal. You’ll find this in the decision notice on the Environmental Registry
  3. Copies of all supporting documents, facts and evidence that you’ll be using to appeal
What is considered

The appeal body will consider the following two questions in deciding whether to grant you leave to appeal:

  1. is there is good reason to believe that no reasonable person, with respect to the relevant law and to any government policies developed to guide decisions of that kind, could have made the decision?
  2. could the decision you wish to appeal result in significant harm to the environment?

2. Provide your notice

You’ll need to provide notice to the Minister of the Environment, Conservation and Parks that you’re seeking leave to appeal.

In your notice, please include a brief description of the:

  • decision that you wish to appeal
  • grounds for granting leave to appeal

You can provide notice by email at minister.mecp@ontario.ca or by mail at:

College Park 5th Floor, 777 Bay St.
Toronto, ON 
M7A 2J3

3. Mail your application

You’ll need to mail your application that you prepared in step #1 to each of these three parties:

  • appellate body
  • issuing authority (the ministry official who issued the instrument)
  • proponent (the company or individual to whom the instrument was issued)

Issuing authority
Amy Shaw
Guelph District Office Manager

Regional Offices - Guelph District Office
Ontario Government Building, 4th Floor
1 Stone Road West
Guelph, ON
N1G 4Y2
Canada

519-826-4258

Proponent(s)

Suncor Energy Inc.
3275 Rebecca Street
Oakville, ON
L6L 6N5
Canada

Suncor Energy Products Partnership
2489 North Sheridan Way
Mississauga, ON
L5K 1A8
Canada


Appellate body

Environmental Review Tribunal
Attention: The Secretary
655 Bay Street
Floor 15
Toronto, Ontario
M5G 1E5
(416) 212-6349
(866) 448-2248
OLT.Registrar@ontario.ca

About the Environmental Review Tribunal


Include the following:

ERO number
019-2040
Ministry reference number
7232-BPZQMQ

This is not legal advice. Please refer to the Environmental Bill of Rights for exact legal requirements. Consult a lawyer if you need help with the appeal process.

Connect with us

Contact

Sign up for notifications

We will send you email notifications with any updates related to this consultation. You can change your notification preferences anytime by visiting settings in your profile page.

Follow this notice

Original proposal

ERO number
019-2040
Ministry reference number
7232-BPZQMQ
Notice type
Instrument
Act
Environmental Protection Act, R.S.O. 1990
Posted by
Ministry of the Environment, Conservation and Parks
Proposal posted

Comment period

July 6, 2020 - August 20, 2020 (45 days)

Proposal details

A risk assessment was undertaken for this property to establish the risks that the contaminants identified in the risk assessment may pose to future users and to identify appropriate risk management measures to be implemented to ensure that the property is suitable for the intended "residential” use as defined by Ontario Regulation 153/04.

The ministry’s review of the risk assessment involved the following reports, documents and information /correspondence:

  • Risk Assessment Pre-submission: 290 Woolwich Street, Guelph, Ontario. Prepared by Terrapex Environmental Ltd., dated August 31, 2017
  • Site-Specific Risk Assessment: 290 Woolwich Street, Guelph, Ontario. Prepared by Terrapex Environmental Ltd., dated July 16, 2018
  • Revised Site-Specific Risk Assessment: 290 Woolwich Street, Guelph, Ontario. Prepared by Terrapex Environmental Ltd., dated January 3, 2019
  • Revised Site-Specific Risk Assessment: 290 Woolwich Street, Guelph, Ontario. Prepared by Terrapex Environmental Ltd., dated November 29, 2019
  • Email RE: Request for Additional Information for Risk Assessment for 290 Woolwich Street, Guelph, ON [RA1658-17c; IDS #3222-ARKFHB]. From Kinsie Adams, Terrapex Environmental Ltd., received by TASDB on April 9, 2020, with following documents attached:
    • CB780.00_Request_Additional_Information_03252020
    • CB780.00 - SSRA - 290 Woolwich St Guelph - 2020-04-08

Based on the documents provided to the ministry as part of the risk assessment report, the reviewers can confirm that the risk assessment has been conducted in accordance with the Environmental Protection Act, Ontario Regulation 153/04 and the associated guidance documents.

The director provided the proponent with written Notice of the Director’s Decision to accept the risk assessment No. 3222-ARKFHB relating to the property in accordance with s. 168.5 of the act on April 15, 2020.

The director is considering the issuance of a Certificate of Property Use (CPU) in relation to the site. The proposed CPU incorporates the risk management measures proposed in the risk assessment and additional conditions proposed by the director and is attached to this notice.

All comments will be considered as part of the decision-making by the ministry if they:

  1. are submitted in writing
  2. reference both the ERO Number and the ministry Instrument Reference
  3. are received by the contact person within the specified comment period

No acknowledgement or individual response will be provided to those who comment.

Supporting materials

View materials in person

Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.

Get in touch with the office listed below to find out if materials are available.

Comment

Commenting is now closed.

This consultation was open from July 6, 2020
to August 20, 2020

Connect with us

Contact