An Environmental Compliance Approval (Waste Site) 20-KEN-82275 for Asselin Transportation and Storage Ltd. was issued

ERO number
019-2849
Notice type
Bulletin
Act
Environmental Protection Act, R.S.O. 1990
Posted by
Ministry of the Environment, Conservation and Parks
Bulletin posted
Last updated

This notice is for informational purposes only. There is no requirement to consult on this initiative on the Environmental Registry of Ontario. Learn more about the types of notices on the registry.

Bulletin summary

An Environmental Compliance Approval (waste site) 20-KEN-82275 for Asselin Transportation and Storage Ltd. was issued on November 24, 2020 for a hauled sewage site in the Township of Fleming, Ontario.

Why consultation isn't required

On April 1, 2020, the Ontario Government made a temporary regulation to respond to the COVID-19 outbreak. Ontario Regulation 115/20 exempts all proposals for policies, acts, regulations and instruments from posting requirements under the EBR.

Ontario Regulation 115/20 was revoked on June 15, 2020, however, we are posting this decision as a bulletin because the proposal was posted on original posting date, while Ontario Regulation 115/20 was in effect.

Although consultation was not required, the ministry did consult with the public on this proposal by posting ERO # 019-1654 for public comment from April 20, 2020 – June 4, 2020. To ensure transparency, the ministry is providing details of its decision and the effects of consultation on decision-making in this notice.

Bulletin details

Proponent

Asselin Transportation and Storage Ltd.
174, Highway 11, PO BOX 746
Fort Frances, ON, P9A 3N1

Location details

Site Location: Highway 11, Township of Fleming (see map of site location)

To see the site location on a map, refer to the instrument proposal under ERO # 019-1654.

Instrument decision

Application type: renewal

Total useable area: 0.5 hectares

Type of disposal: 2 dewatering trench

Operational requirements

Conditions on the Environmental Compliance Approval include requirements to develop and follow spill response procedures, train staff and maintain records. The approval also includes the following operational requirements:

  • prior to operating at the site, the company shall develop written procedures covering the following:
    • procedures for reporting to the ministry, and municipal authorities as required in the event a spill occurs at the site
    • a list of the personnel responsible for operations at the site
  • the company shall ensure that all personnel involved in the operation of this hauled sewage disposal site are aware of the requirements of this approval and are trained in Spill Prevention
  • spills of a pollutant that cause or may cause an adverse effect are to be reported to the Ministry's Spills Action Centre and the company shall take appropriate remedial action to limit the impact
  • the company must ensure that no unnecessary off-site effects, such as vermin, vectors, odour, dust, litter, noise or traffic, result from the operation of this site
  • written records must be maintained in a log book that documents daily operations as well as any spills that occur and any complaints received
  • the dewatering trenches must be designed and constructed according to specified standards set out in the approval
  • the dewatering trenches must be operated in accordance with specified standards set out in the approval which include maximum volumes that can be put in a trench, rotating the use of the trenches, ensuring trenches have a rest period and cleaning residuals from the trenches on a regular basis
  • a closure plan shall be developed for the site and the site must be closed in accordance with the plan
  • the following types of monitoring conditions will be required: none
  • Financial Assurance will not be required
  • approval expires on December 31, 2030

Other

Prior to the spreading of hauled sewage, the operator is responsible for ensuring that all necessary approvals, licences or permits that may be required from other authorities, such as the local municipality, conservation authority, MNRF and OMAFRA, have been acquired.

Comments received

No comments were received.

Effects of consultation

Since we did not receive any comment during the commenting period, there is no impact of comment on the approval.

Third parties are not able to apply for leave to appeal in respect of proposals which were posted while Ontario Regulation 115/20 was in effect between April 1, 2020 and June 14, 2020. Ontario Regulation 115/20 exempted all proposals for instruments from posting requirements under the EBR. Leave to appeal may only be sought in respect of instruments that are required to be posted to the ERO.

Appeal information

Appeals are not allowed. This instrument type cannot be appealed.

Supporting materials

View materials in person

Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.

Get in touch with the office listed below to find out if materials are available.

Connect with us

Contact

Sign up for notifications

We will send you email notifications with any updates related to this consultation. You can change your notification preferences anytime by visiting settings in your profile page.

Follow this notice