Proposed amendment to regulations under the Ontario Energy Board Act, 1998 to further streamline approvals for pipeline relocations or reconstructions to build infrastructure projects faster.

ERO number
019-9384
Notice type
Regulation
Act
Ontario Energy Board Act, 1998
Posted by
Ministry of Energy and Mines
Notice stage
Decision
Decision posted
Comment period
November 13, 2024 - December 28, 2024 (45 days) Closed
Last updated

This consultation was open from:
November 13, 2024
to December 28, 2024

Decision summary

It was decided to further streamline OEB approvals for any hydrocarbon pipeline relocations and reconstructions that are requested by a third-party (i.e., other than the pipeline owner).

Decision details

Ontario decided to amend Ontario Regulation 328/03 to allow the OEB to determine that Leave to Construct (LTC) approval is not required for any hydrocarbon pipeline relocation or reconstruction requested by a third-party, subject to all existing conditions currently required by the Regulation such as control of land, cost agreement and Indigenous consultation.

What Does This Mean?

Prior to July 1, 2025, under Ontario Regulation 328/03, any existing intra-provincial hydrocarbon pipeline (i.e., natural gas or petroleum products pipeline solely within Ontario) being relocated or reconstructed required LTC approval from the OEB in the following situations:

  1. The diameter of the pipeline is increased;
  2. The acquisition of additional land or authority to use additional land is necessary, except where, on application, the OEB determines that leave to construct is not required because:
    1. The pipeline relocation or reconstruction is facilitating a priority transit project (within the meaning of the Building Transit Faster Act, 2020), or a project by a road authority (within the meaning of the Public Service Works on Highways Act), and
      1. any additional land required for the relocation or reconstruction is under the control of the priority transit project proponent or the road authority, and
      2. the relocation or reconstruction is undertaken pursuant to an agreement between the pipeline developer (i.e., the applicant) and the priority transit project proponent or road authority that specifies the cost of the relocation is paid wholly or partly by the priority transit project or road authority, and
    2. The OEB determines that the Crown’s duty to consult (DTC), if it applies, has been adequately discharged.

The decision to further amend Ontario Regulation 328/03, effective July 1, 2025, will extend the aforementioned streamlined approach, with identical conditions, to requests for hydrocarbon pipeline relocations or reconstructions from any third-party (i.e., other than the pipeline owner). This could include third-party projects that might require a section of pipeline to be relocated such as other provincially or municipally delivered transit projects, municipal water and sewer projects, flood protection projects, housing developments or projects by rail or marine authorities.

This will help facilitate building the types of infrastructure necessary to grow Ontario’s economy by reducing unnecessary regulatory burden.

Comments received

Through the registry

4

By email

0

By mail

0
View comments submitted through the registry

Effects of consultation

Of the five comments received during the consultation period, three stakeholders from the energy, municipal and agricultural sectors supported the proposal. These stakeholders noted that the same conditions that apply to the current ‘priority transit’ and ‘road authority’ exemptions for requesting to move an existing hydrocarbon pipeline, would apply to requests by other third-parties. They also noted the exemption will help projects proceed faster.

 One Indigenous community had concerns about the proposal’s scope and allowing an LTC exemption for any external relocation request. Concerns were also raised about streamlining processes in general that could lead to erosion of Inherent and Treaty rights through reduced environmental oversight and reduced opportunities for comprehensive consultation.

One comment from a member of the public expressed concerns about creating more traffic and concentrating power into the Province and taking it away from municipalities.

It has been decided to broaden the circumstances under which the OEB can determine that LTC is not required for hydrocarbon pipeline relocation and reconstruction. Rather than being limited to ‘priority transit’ and ‘road authority’ projects, we are expanding the streamlined approval approach to any third-party requests, subject to the same conditions that currently exist in Ontario Regulation 328/03. The OEB will continue to make a determination that the Crown’s DTC with Indigenous communities, if triggered, has been adequately discharged. 

Connect with us

Contact

Sign up for notifications

We will send you email notifications with any updates related to this consultation. You can change your notification preferences anytime by visiting settings in your profile page.

Follow this notice

Original proposal

ERO number
019-9384
Notice type
Regulation
Act
Ontario Energy Board Act, 1998
Posted by
Ministry of Energy
Proposal posted

Comment period

November 13, 2024 - December 28, 2024 (45 days)

Proposal details

This posting seeks to receive feedback on a proposal by the Ministry of Energy and Electrification (ENERGY) to amend regulations under the Ontario Energy Board Act, 1998 (OEBA) to further streamline the Ontario Energy Board (OEB) approval process for pipeline relocations or reconstructions that support housing, transit and other infrastructure projects beyond those currently designated in Ontario Regulation 328/03.

Currently, the OEBA allows the OEB to determine that leave-to-construct (LTC) is not required for certain relocation or reconstruction of electricity transmission and distribution lines, and for relocation or reconstruction of pipelines subject to conditions in regulation. Broadening the circumstances in which the OEB can determine that LTC is not required for pipeline relocation or reconstruction would support the government-wide efforts to address timelines related to essential infrastructure projects including building transit and homes faster.

Background

As the government commits to building new housing and transit projects, relocating existing natural gas pipelines can take a significant amount of time for regulatory approvals, even in instances when a utility is moving the infrastructure a short distance such as to the other side of the street or a parallel street. This can add time delays to a construction project.

In June 2024, the Cutting Red Tape to Build More Homes Act, 2024, received Royal Assent, which, among other things, amended the OEBA to provide the government with authority to prescribe in regulation when LTC approval from the OEB would be required for a pipeline relocation or reconstruction project.

Subsequently, the government amended section 3 of Ontario Regulation 328/03, effective July 1, 2024, that LTC would be required for any pipeline relocation or reconstruction only if:

  1. The diameter of the line is increased; or,
  2. The acquisition of additional land or authority to use additional land is necessary except when,
    • the relocation or reconstruction is to facilitate a priority transit project or a project by a road authority and any additional land required is under the control of the priority transit project proponent or the road authority; and,
    • the relocation or reconstruction is pursuant to an agreement between the pipeline owner and priority transit project proponent or road authority that specifies that the cost of the relocation or reconstruction is to be paid for wholly or partly by the priority transit project proponent or the road authority; and,
    • the OEB makes a determination that the Crown’s duty to consult (DTC), if it applies, has been adequately discharged.

We previously posted these legislative and regulatory proposals for consultation on the Environmental Registry of Ontario (ERO).

The effect of the legislative and regulatory changes on July 1, 2024, was to modernize LTC approvals for pipeline relocations and reconstructions to support building transit and housing faster. Prior to the change, LTC was required for pipeline relocations or reconstructions if the diameter of the line changed (either increased or decreased) or if the acquisition of land or authority to use additional land was necessary (without exception).

Current Proposal

We have heard from stakeholders that a streamlined OEB approval process can also benefit pipeline relocations and reconstructions that facilitate other infrastructure and related projects. The current regulation only allows for exceptions from the OEB’s LTC requirements for pipeline relocations and reconstructions supporting priority transit projects and projects by a road authority.

We are seeking feedback on a proposal to make additional regulatory changes such that the OEB can determine that the requirement to obtain LTC approval does not apply to pipeline relocations or reconstructions that facilitate any type of infrastructure project or external relocation request, subject to the same conditions currently in place in section 3 of Ontario Regulation 328/03 (i.e., control of land, cost allocation and the OEB making a determination that the Crown’s DTC, if it applies, has been adequately discharged).

Examples of these infrastructure projects or external relocation requests to a pipeline owner could include other provincially or municipally delivered transit projects, municipal water and sewer projects, flood protection projects, housing developments or projects by rail or marine authorities.

Environmental Impact

The proposal is not anticipated to have a significant impact on the environment. While certain infrastructure projects or other work facilitated by pipeline relocations may have environmental impacts, the infrastructure or related projects are subject to their own environmental review requirements outside of OEB jurisdiction. Similarly, all relevant permits and approvals to ensure environmental, technical and safety requirements from Ontario ministries, authorities and municipalities would still need to be met before proceeding with pipeline relocations or reconstructions.

There are no new administrative costs for business. The proposed broadening of exemption from leave-to-construct for certain pipeline relocation or reconstruction would aim to reduce costs and timelines for pipeline developers compared to the OEB’s current leave-to-construct process.

Supporting materials

View materials in person

Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.

Get in touch with the office listed below to find out if materials are available.

Comment

Commenting is now closed.

This consultation was open from November 13, 2024
to December 28, 2024

Connect with us

Contact