G. TACKABERRY & SONS CONSTRUCTION COMPANY LIMITED - Permit to take water

Instrument type: Permit to take water

ERO number
026-0582
Ministry reference number
1000444056
Notice type
Instrument
Act
Ontario Water Resources Act, R.S.O. 1990
Posted by
Ministry of the Environment, Conservation and Parks
Notice stage
Proposal
Proposal posted
Comment period
May 29, 2026 - June 28, 2026 (30 days) Open
Last updated

This consultation closes at 11:59 p.m. on:
June 28, 2026

Proposal summary

This proposal is for a renewal to Permit to Take Water No. 4360-ACUNG2 for G. TACKABERRY & SONS CONSTRUCTION COMPANY LIMITED. Water will be taken from five ponds for mining-aggregate washing, construction-dust suppression and construction purposes, located in the Township of Leeds and The Thousand Islands, Ontario.

Location details

Site address

3299 County Road 32
Leeds and the Thousand Islands, ON
Canada

Site location map

The location pin reflects the approximate area where environmental activity is taking place.

View this location on a map opens link in a new window

Proponent(s)

G. TACKABERRY & SONS CONSTRUCTION COMPANY LIMITED
109 Washburn Road
Athens, ON
K0E 1B0
Canada

Proposal details

This proposal is for a renewal to Permit to Take Water No. 4360-ACUNG2 for G. TACKABERRY & SONS CONSTRUCTION COMPANY LIMITED. Water will be taken from five ponds for/to mining aggregate washing, construction dust suppression and construction purposes, located in the Township of Leeds and The Thousand Islands, Ontario. Details of the water taking are as follows:

Permit type – Renewal

Source Name: Sweet’s Pit

  • Purpose of Taking: Mining - Aggregate Washing
  • Maximum rate per minute (litres): 1,420
  • Maximum number of hours taking a day: 24
  • Maximum rate per minute (litres): 2,044,800
  • Maximum number of days of taking per year: 292
  • Earliest calendar date of taking (mm/dd): 03/15
  • Latest calendar date of taking (mm/dd): 12/31
  • Period of taking: 10 years

Source Name: Sweet’s Pit (Dust Suppression)

  • Purpose of Taking: Construction - Dust Suppression
  • Maximum rate per minute (): 1,500
  • Maximum number of hours taking a day: 12
  • Maximum volume per day (litres): 525,000
  • Maximum number of days of taking per year: 292
  • Earliest calendar date of taking (mm/dd): 03/15
  • Latest calendar date of taking (mm/dd): 12/31
  • Period of taking: 10 years

Source Name: Sweet’s Pit (Construction)

  • Purpose of Taking: Mining - Construction
  • Maximum rate per minute (litres): 1,500
  • Maximum number of hours taking a day: 12
  • Maximum volume per day (litres): 525,000
  • Maximum number of days of taking per year: 292
  • Earliest calendar date of taking (mm/dd): 03/15
  • Latest calendar date of taking (mm/dd): 12/31
  • Period of taking: 10 years

Source Name: North Settling Pond

  • Purpose of Taking: Mining - Aggregate Washing
  • Maximum rate per minute (litres): 5,455
  • Maximum number of hours taking a day: 24
  • Maximum volume per day (litres): 7,855,200
  • Maximum number of days of taking per year: 292
  • Earliest calendar date of taking (mm/dd): 03/15
  • Latest calendar date of taking (mm/dd): 12/31
  • Period of taking: 10 years

Source Name: South Settling Pond

  • Purpose of Taking: Mining - Aggregate Washing
  • Maximum rate per minute (litres): 5,455
  • Maximum number of hours taking a day: 24
  • Maximum volume per day (litres): 7,855,200
  • Maximum number of days of taking per year: 292
  • Earliest calendar date of taking (mm/dd): 03/15
  • Latest calendar date of taking (mm/dd): 12/31
  • Period of taking: 10 years

Source Name: Pond A

  • Purpose of Taking: Mining - Aggregate Washing
  • Maximum rate per minute (litres): 5,455
  • Maximum number of hours taking a day: 24
  • Maximum volume per day (litres): 7,855,200
  • Maximum number of days of taking per year: 292
  • Earliest calendar date of taking (mm/dd): 03/15
  • Latest calendar date of taking (mm/dd): 12/31
  • Period of taking: 10 years

Source Name: Pond A (Dust Suppression)

  • Purpose of Taking: Construction – Dust Suppression
  • Maximum rate per minute (litres): 1,500
  • Maximum number of hours taking a day: 12
  • Maximum volume per day (litres): 525,000
  • Maximum number of days of taking per year: 292
  • Earliest calendar date of taking (mm/dd): 03/15
  • Latest calendar date of taking (mm/dd): 12/31
  • Period of taking: 10 years

Source Name: Pond A (Road Construction)

  • Purpose of Taking: Mining - Construction
  • Maximum rate per minute (litres): 1,500
  • Maximum number of hours taking a day: 12
  • Maximum volume per day (litres): 525,000
  • Maximum number of days of taking per year: 292
  • Earliest calendar date of taking (mm/dd): 03/15
  • Latest calendar date of taking (mm/dd): 12/31
  • Period of taking: 10 years

Source Name: Pond B

  • Purpose of Taking: Mining - Aggregate Washing
  • Maximum rate per minute (litres): 5,455
  • Maximum number of hours taking a day: 24
  • Maximum volume per day (litres): 7,855,200
  • Maximum number of days of taking per year: 292
  • Earliest calendar date of taking (mm/dd): 03/15
  • Latest calendar date of taking (mm/dd): 12/31
  • Period of taking: 10 years

Source Name: Pond B (Dust Suppression)

  • Purpose of Taking: Mining - Dust Suppression
  • Maximum rate per minute (litres): 1,500
  • Maximum number of hours taking a day: 12
  • Maximum volume per day (litres): 525,000
  • Maximum number of days of taking per year: 292
  • Earliest calendar date of taking (mm/dd): 03/15
  • Latest calendar date of taking (mm/dd): 12/31
  • Period of taking: 10 years

Source Name: Pond B (Road Construction)

  • Purpose of Taking: Mining - Construction
  • Maximum rate per minute (litres): 1,500
  • Maximum number of hours taking a day: 12
  • Maximum volume per day (litres): 525,000
  • Maximum number of days of taking per year: 292
  • Earliest calendar date of taking (mm/dd): 03/15
  • Latest calendar date of taking (mm/dd): 12/31
  • Period of taking: 10 years

There are 3 categories of a Permit to Take Water:

  • Category 1: water takings are anticipated to have a lower risk of causing an unacceptable environmental impact/interference
  • Category 2: water takings are anticipated to having a higher potential of causing unacceptable environmental impact or interference
  • Category 3: water takings are anticipated to have the highest potential of causing unacceptable environmental impactor interference

The proposed water taking qualifies as a Category 1 permit.

Supporting materials

View materials in person

Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.

Get in touch with the office listed below to find out if materials are available.

Client Services and Permissions Branch
Address

135 St Clair Ave West
1st Floor
Toronto, ON
M4V 1P5
Canada

Office phone number

Comment

Let us know what you think of our proposal.

Have questions? Get in touch with the contact person below. Please include the ERO number for this notice in your email or letter to the contact.

Read our commenting and privacy policies.

Submit online

Submit by mail

Contact

Connect with us

Contact

Sign up for notifications

We will send you email notifications with any updates related to this consultation. You can change your notification preferences anytime by visiting settings in your profile page.

Follow this notice