Permit PR-17-11207 has been issued on September 6, 2019. This exploration permit is valid for 3 years from the date of issue.
Location details
Site location details
To view individual claims on a map please use the Mining Lands Administration System. Click on “I want to…” and select “Find a claim” to search by claim numbers or "Find a township" to search by township.
Claim numbers: 4270038, 4270039, 4270040, 4270555, 4270557, 4270558, 4270043, 4270042, 4270041, 4270556, 4270044, 4270045, 4270559, 4270560, 4270047, 4270048, 4270049, 4270550, 4270551, 4270563, 4281382, 4281385, 4281384, 4281383, 4270554, 4270553, 4270552, 4281386, 4281387, 4281374, 4281388, 4281375, 4281369, 4281376, 4281370, 4281371, 4281372, 4270613, 4270614, 4270615, 4270617, 4270618
Site location map
The location pin reflects the approximate area where environmental activity is taking place.
View this location on a map opens link in a new windowProponent(s)
Rudolf Wahl
47 Graham Crescent
Po Box 1022
Marathon,
ON
P0T 2E0
Canada
Decision details
Permit PR-17-11207 has been issued on September 6, 2019. This exploration permit is valid for 3 years from the date of issue.
Effects of consultation
No comments received resulting in no impact on the decision whether or not to proceed with this proposal.
Supporting materials
View materials in person
Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.
Get in touch with the office listed below to find out if materials are available.
435 James Street South
Suite B002
Thunder Bay,
ON
P7E 6E3
Canada
How to Appeal
Appeals are not allowed
This instrument type cannot be appealed. Learn more about our consultation process.
Connect with us
Contact
Andrew Kane
435 James Street South
Suite B002
Thunder Bay,
ON
P7E 6E3
Canada
Original proposal
Proposal details
Description of instrument
Rudolf Wahl has submitted an application to MENDM as required under the Mining Act for prescribed early exploration activities. The project is situated approximately 350km East of Thunder Bay, Ontario.
The activities that this permit would allow Rudolf Wahl to carry out are as follows:
- 11-20 pads for mechanized drilling (assembled weight >150kg)
- mechanized stripping (approximately 100m2 in 200 metre radius)
- pitting and trenching of bedrock (20 planned pits/trenches)
- line cutting 50,000 m
An Exploration Permit does not relieve the proponent from compliance with any other requirements that are set out under the Mining Act or any other Act. Further all activities included in the Exploration Permit proposal must be carried out in compliance with O Reg. 308/12 and the Provincial Standards for Early Exploration.
The Exploration Permit duration will be up to 3 years with the possibility of one renewal for up to 3 years.
Supporting materials
View materials in person
Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.
Get in touch with the office listed below to find out if materials are available.
933 Ramsey Lake Road
Level B6
Sudbury,
ON
P3E 6B5
Canada
Comment
Commenting is now closed.
This consultation was open from November 8, 2017
to December 8, 2017
Connect with us
Contact
Andrew Kane
435 James Street South
Suite B002
Thunder Bay,
ON
P7E 6E3
Canada
Comments received
Through the registry
0By email
0By mail
0