Decision summary
Approval was granted for a major site plan amendment to allow St. Marys Cement Inc. Canada to revise the sequence of operational phasing for the ARA licence #624927 (Bromberg Pit).
Location details
Site location details
Part Lot 33 and 34, Concession 9, Township of North Dumfries, Region of Waterloo
The site is Aggregate Resources Act (ARA) licence #624927
A link showing sites licensed under the Aggregate Resources Act is provided: ontario.ca - find pits and quarries
Proponent(s)
St. Marys Cement Incorporated Canada
55 Industrial Street
Toronto,
ON
M4G 3W9
Canada
Decision details
Approval was granted by the Regional Director on August 9, 2019.
Effects of consultation
Written comments were received from the three agencies. The Township of North Dumfries and Region of Waterloo indicated in writing that they had no concerns. The MNRF commented on the implementation of the natural heritage system and requested updates to the technical notes on the site plan. The MNRF interests were addressed through correspondence with the project team and through revisions to the site plan.
A decision was made to proceed with the approval of this proposal.
Supporting materials
View materials in person
Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.
Get in touch with the office listed below to find out if materials are available.
1 Stone Road West
Guelph,
ON
N1G 4Y2
Canada
How to Appeal
Appeals are not allowed
This instrument type cannot be appealed. Learn more about our consultation process.
Connect with us
Contact
Seana Richardson
1 Stone Road West
Guelph,
ON
N1G 4Y2
Canada
Original proposal
Proposal details
St. Marys Cement Inc. Canada has submitted a site plan amendment request to revise the sequence of operational phasing for the Bromberg Pit ARA licence #624927.The proposed changes to the site plan will allow extraction of Phase 2 and 3 simultaneously and the blending of materials between phases. The order of extraction in Phase 3a and Phase 3b would also be reversed thereby delaying the removal of a remaining woodlot until Phase 2 is ready for rehabilitation and to receive the woodland soils removed from the new Phase 3b. St. Marys is also requesting to expand and join Phase 1 and 2 and relocate the access road into Phase 2 south of an existing pond. This will avoid disturbing an area of Phase 1 that is already rehabilitated.
Other information
St. Marys Cement currently operates this site under the authority of licence # 624927 under the Aggregate Resources Act.
Site plan information is available to view at the Ministry of Natural Resources and Forestry, Guelph District Office. Making an appointment to view the information is recommended to ensure aggregate staff will be available to provide information and answer questions.
Public consultation opportunities
The application has been circulated to the Township of North Dumfries, the Region of Waterloo and Ministry of Natural Resources and Forestry – Guelph District for comment.
Supporting materials
View materials in person
Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.
Get in touch with the office listed below to find out if materials are available.
1 Stone Road West
Guelph,
ON
N1G 4Y2
Canada
Comment
Commenting is now closed.
This consultation was open from May 23, 2019
to June 24, 2019
Connect with us
Contact
Seana Richardson
1 Stone Road West
Guelph,
ON
N1G 4Y2
Canada
Comments received
Through the registry
0By email
3By mail
0