This consultation was open from:
August 2, 2019
to September 1, 2019
Decision summary
The Exploration Permit was issued and is valid for a period of 3 years.
Location details
Site location details
To view individual claims on a map please use the Mining Lands Administration System. Click on “I want to…” and select “Find a claim” to search by claim numbers or "Find a township" to search by township.
These activities are located approximately 39 kilometres northeast of White River and approximately 39 kilometres southwest of Hornepayne in Gourlay and Hambleton Townships
Claim numbers: 531228, 531230,531231,531243,531244, 531247, 531248, 531249
Site location map
The location pin reflects the approximate area where environmental activity is taking place.
View this location on a map opens link in a new windowProponent(s)
Harte Gold Corporation
113 Tukanee Lake Road
P.O. Box 267
White River,
ON
P0M 3G0
Canada
Decision details
The Exploration Permit was issued once all Aboriginal communities and the public had the opportunity to provide comment or raise their concerns. The accepted Exploration Permit is valid for a period of 3 years.
Effects of consultation
No comments were received through the ERO resulting in no impact on the decision whether or not to proceed with this proposal.
Supporting materials
View materials in person
Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.
Get in touch with the office listed below to find out if materials are available.
5520 Highway 101 E Highway
PO Box 3060
South Porcupine Ontario,
ON
P0N 1H0
Canada
How to Appeal
Appeals are not allowed
This instrument type cannot be appealed. Learn more about our consultation process.
Connect with us
Contact
Susan Thorne
5520 Highway 101 E Highway
PO Box 3060
South Porcupine Ontario,
ON
P0N 1H0
Canada
Original proposal
Proposal details
Harte Gold Corp. has submitted an application to MENDM as required under the Mining Act for prescribed early exploration activities.
The activities that this permit would allow Harte Gold Corp. to carry out are as follows:
Plan Activities
- geophysical Survey Requiring Generator Type
- line Cutting (<1.5m width)
Permit Activities
- mechanized Drilling (Assembled Weight >150kg
An Exploration Permit does not relieve the proponent from compliance with any other requirements that are set out under the Mining Act or any other Act. Further all activities included in the Exploration Permit proposal must be carried out in compliance with O. Reg. 308/12 and the Provincial Standards for Early Exploration.
The Exploration Permit duration will be up to 3 years with the possibility of one renewal for up to 3 years.
Supporting materials
View materials in person
Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.
Get in touch with the office listed below to find out if materials are available.
5520 Highway 101 E Highway
PO Box 3060
South Porcupine Ontario,
ON
P0N 1H0
Canada
Comment
Commenting is now closed.
This consultation was open from August 2, 2019
to September 1, 2019
Connect with us
Contact
Susan Thorne
5520 Highway 101 E Highway
PO Box 3060
South Porcupine Ontario,
ON
P0N 1H0
Canada
Comments received
Through the registry
0By email
0By mail
0