This consultation was open from:
August 23, 2019
to September 22, 2019
Decision summary
The Exploration Permit was issued and is valid for a period of 3 years.
Location details
Site location details
These activities are located approximately 22 kilometres northwest of the town of Cobalt within the townships of Barr and Lundy.
To view individual claims on a map please use the Mining Lands Administration System. Click on “I want to…” and select “Find a claim” to search by claim numbers or "Find a township" to search by township.
Claim Number: 555190
Site location map
The location pin reflects the approximate area where environmental activity is taking place.
View this location on a map opens link in a new windowProponent(s)
The Claim Group Inc.
26 Brimley Ct
Belleville,
ON
K8N 5L5
Canada
Decision details
The Exploration Permit was issued once all Aboriginal communities and the public had the opportunity to provide comment or raise their concerns. The accepted Exploration Permit is valid for a period of 3 years.
Effects of consultation
No comments were received resulting in no impact on the decision whether or not to proceed with this proposal.
Supporting materials
View materials in person
Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.
Get in touch with the office listed below to find out if materials are available.
PO Bag 3060, 5520 Hwy 101 East
South Porcupine,
ON
P0N 1H0
Canada
How to Appeal
Appeals are not allowed
This instrument type cannot be appealed. Learn more about our consultation process.
Connect with us
Contact
Aisha Samuel
5520 Highway 101 East
PO Box 3060
South Porcupine,
ON
P0N 1H0
Canada
Original proposal
Proposal details
The Claim Group Inc. has submitted applications to The Ministry of Energy, Northern Development and Mines as required under the Mining Act for prescribed early exploration activities.
The activities that the permit would allow The Claim Group Inc. to carry out are as follows:
Permit Activities:
- mechanized Drilling (Assembled Weight >150 kilograms)
An Exploration Permit does not relieve the proponent from compliance with any other requirements that are set out under the Mining Act or any other Act. Further all activities included in the Exploration Permit proposal must be carried out in compliance with O. Reg. 308/12 and the Provincial Standards for Early Exploration.
The Exploration Permit duration will be up to 3 years with the possibility of one renewal for up to 3 years.
Supporting materials
View materials in person
Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.
Get in touch with the office listed below to find out if materials are available.
PO Bag 3060, 5520 Hwy 101 East
South Porcupine,
ON
P0N 1H0
Canada
Comment
Commenting is now closed.
This consultation was open from August 23, 2019
to September 22, 2019
Connect with us
Contact
Aisha Samuel
5520 Highway 101 East
PO Box 3060
South Porcupine,
ON
P0N 1H0
Canada