Update Announcement
A decision for this proposal has been published as a Bulletin under ERO 019-3610 on May 10, 2021.
This consultation was open from:
April 1, 2020
to May 1, 2020
Proposal summary
This new permit application is for the temporary dewatering for the construction of a proposed residential development.
Location details
Site address
CLARENCE,
ON
K4K 1P6
Canada
Site location details
Lot C, Concession 8.
Site location map
The location pin reflects the approximate area where environmental activity is taking place.
View this location on a map opens link in a new windowProponent(s)
Spacebuilders Ottawa Ltd.
345 Laurier Street
C box 849
Rockland,
ON
K4K 1L5
Canada
Why consultation isn't required
On April 1, 2020, the Ontario Government made a temporary regulation to respond to the COVID-19 outbreak. Ontario Regulation 115/20 exempts all proposals for policies, acts, regulations and instruments from posting requirements under the EBR until 30 days after the declared emergency is terminated.
Proposal details
This proposal is for a new Permit to Take Water for the temporary dewatering for the construction of the proposed Morris Village residential development (Stage 5) in the Municipality of Clarence-Rockland. Water will be taken for dewatering of construction excavations to allow for geotechnically sound excavations and provide a safe working environment for those within the excavations.
The groundwater that is removed from the excavations at the subject site is intended to be discharged to the ground surface where it will be re-infiltrated into the overburden.
The taking of water is as follows:
Source name: S1 - building excavation
- purpose of taking: construction/dewatering
- maximum rate per minute (litres per minute): 5,600
- maximum number of hours of taking per day: 24
- maximum volume of taking per day: 1,000,000 litres
- maximum number of days of taking in a year: 365
- earliest calendar date of taking (mm/dd): 06/01
- latest calendar date of taking (mm/dd): 05/01
- length of taking: 9 years
Source name: S2 - site servicing
- purpose of taking: construction/dewatering
- maximum rate per minute (litres per minute): 5,600
- maximum number of hours of taking per day: 24
- maximum volume of taking per day: 1,000,000 litres
- maximum number of days of taking in a year: 365
- earliest calendar date of taking (mm/dd): 06/01
- latest calendar date of taking (mm/dd): 05/31
- length of taking: 9 years
Source name: S3 - pump station
- purpose of taking: construction/dewatering
- maximum rate per minute (litres per minute): 5,600
- maximum number of hours of taking per day: 24
- maximum volume of taking per day: 3,000,000 litres
- maximum number of days of taking in a year: 365
- earliest calendar date of taking (mm/dd): 06/01
- latest calendar date of taking (mm/dd): 05/31
- length of taking: 1 years
Source name: S4 - SWMP
- purpose of taking: construction/dewatering
- maximum rate per minute (litres per minute): 14,000
- maximum number of hours of taking per day: 24
- maximum volume of taking per day: 10,000,000 litres
- maximum number of days of taking in a year: 365
- earliest calendar date of taking (mm/dd): 6/01
- latest calendar date of taking (mm/dd): 05/31
- length of taking: 1 years
Source name: S5 - Lafontaine Creek - East Branch
- purpose of taking: construction/dewatering
- maximum rate per minute (litres per minute): 5,600
- maximum number of hours of taking per day: 24
- maximum volume of taking per day: 1,000,000 litres
- maximum number of days of taking in a year: 365
- earliest calendar date of taking (mm/dd): 01/01
- latest calendar date of taking (mm/dd): 12/31
- length of taking: 2 years
Supporting materials
View materials in person
Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.
Get in touch with the office listed below to find out if materials are available.
1259 Gardiners Road
Unit 3
Kingston,
ON
K7P 3J6
Canada
Connect with us
Contact
Permit to Take Water Coordinator (Eastern Region)
1259 Gardiners Road
Unit 3
Kingston,
ON
K7P 3J6
Canada