Decision summary
The Director of Exploration has made a decision on the exploration permit application PR-23-000149 to EV Nickel Incorporated for early exploration activities approximately 35 kilometres southeast of Timmins, Ontario, in Langmuir townships, District of Cochrane, Northeast Region.
The decision is to issue.
Location details
Site location details
The mining activities are located approximately 37 kilometres southeast of Timmins, Ontario, in Langmuir township, District of Cochrane, Northeast Region.
To view individual claims on a map please use the Mining Lands Administration System. Click on “I want to…” and select “Find a claim” to search by claim numbers or “Find a township” to search by township.
Claim numbers: 149608, 186924, 214435, 252374, 264368, 299464, 299485, 341088
Site location map
The location pin reflects the approximate area where environmental activity is taking place.
View this location on a map opens link in a new windowProponent(s)
EV Nickel Incorporated
44 Victoria Street
Suite 1612
Toronto,
ON
M5C 1Y2
Canada
Decision details
On September 19, 2023, the ministry issued an exploration permit approximately 37 kilometres southeast of Timmins, Ontario, in Langmuir townships, District of Cochrane, Northeast Region.
This permit will allow the company to conduct:
- mechanized drilling (where the drill weight is greater than 150 kilograms)
Plan activities
- geophysical survey requiring generator type
The exploration permit was issued once all Indigenous communities and the public had the opportunity to provide comment or raise their concerns. The Exploration Permit duration will be up to 3 years with the possibility of renewal.
Effects of consultation
No comment was received through the Environmental Registry of Ontario resulting in no impact on the decision to proceed or not with this proposal.
Supporting materials
View materials in person
Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.
Get in touch with the office listed below to find out if materials are available.
5520 Highway 101 East
PO Box 3060
South Porcupine,
ON
P0N 1H0
Canada
How to Appeal
Appeals are not allowed
This instrument type cannot be appealed. Learn more about our consultation process.
Connect with us
Contact
Owen Rigg
5520 Highway 101 E Highway
PO Box 3060
South Porcupine Ontario,
ON
P0N 1H0
Canada
Original proposal
Proposal details
EV Nickel Incorporated has submitted an application to the ministry for an exploration permit as required under the Mining Act for prescribed early exploration activities.
The activities that this permit would allow EV Nickel Incorporated to carry out are as follows:
Plan activities
- geophysical survey requiring generator type
Permit activities
- mechanized drilling (assembled weight greater than 150 kilograms)
The potential disturbance from the activities are described as:
Drilling: provides rock samples from below the surface. Testing the samples determines the properties of the soil and rocks, including mineral and metal content. Potential environmental disturbances include (but are not limited to): clearing surface terrain for “drill pads” (small areas cleared for drill rigs and/or helicopters), installing casings (hollow steel pipes called the collar), and pumping water from a sump, nearby lakes, rivers or streams.
Proponents are required to follow provincial standards for early exploration to minimize the impacts to public health, safety and the environment from early exploration activities described above. You can find the standards in the Activities Information Sheets or on the Ministry website under Mining Act Policies, Standards and Directives (see links in “Related links” section).
This notice is provided to receive comments that can be considered in the decision-making process prior to the issuance of an exploration permit.
An Exploration Permit does not relieve the proponent from compliance with any other requirements that are set out under the Mining Act or any other Act. All activities included in the Exploration Permit proposal must be carried out in compliance with Ontario Regulation 308/12 and the Provincial Standards for Early Exploration. The Exploration Permit duration will be up to 3 years with the possibility of one renewal for up to three years.
Supporting materials
View materials in person
Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.
Get in touch with the office listed below to find out if materials are available.
5520 Highway 101 East
PO Box 3060
South Porcupine,
ON
P0N 1H0
Canada
Comment
Commenting is now closed.
This consultation was open from May 18, 2023
to June 17, 2023
Connect with us
Contact
Owen Rigg
5520 Highway 101 E Highway
PO Box 3060
South Porcupine Ontario,
ON
P0N 1H0
Canada
Comments received
Through the registry
0By email
0By mail
0