Decision summary
An Environmental Compliance Approval with Limited Operational Flexibility (air & noise) was granted to NUCOR STEEL ULC, for its bar and wire mesh products facility, located at 5400 Harvester Road in Burlington, Ontario.
The facility production limit is 294,000 tonnes of steel bar and wire mesh products per year.
Location details
Site address
5400 Harvester Road
Burlington,
ON
Canada
Site location map
The location pin reflects the approximate area where environmental activity is taking place.
View this location on a map opens link in a new windowProponent(s)
NUCOR STEEL ULC
5400 Harvester Road
Burlington,
ON
L7L 5N5
Canada
Decision details
An Environmental Compliance Approval with Limited Operational Flexibility (air & noise) was granted to NUCOR STEEL ULC, for its bar and wire mesh products facility, located at 5400 Harvester Road in Burlington, Ontario.
The facility production limit is 294,000 tonnes of steel bar and wire mesh products per year.
The emission sources from the manufacturing and associated processes that discharge to the air include coil blasting, drawing machines, teurema line, galvanizing line, mesh line, mesh fabrication, exhaust stacks from dust collectors, general building roof vents and exhaust fans, cooling towers, boiler and emergency generators.
Emissions to the air from this facility include:
- suspended particulate matter,
- trace metals,
- nitrogen oxides, and
- noise
The Environmental Compliance Approval with Limited Operational Flexibility (air & noise) requires that the company demonstrate compliance on an ongoing basis with Ontario Regulation 419/05, applicable Ministry Guidelines for Air and Noise and other performance requirements as specified in their conditions. It permits modifications such as process changes, de-bottlenecking or addition of new equipment subject to limits on operational flexibility that include a production limit for the facility to be specified on the Environmental Compliance Approval with Limited Operational Flexibility (air & noise).
The Limited Operational Flexibility conditions will expire 10 years from the date of the Approval, unless this Approval is revoked prior to the expiry date. The company will be required to make application for amendment at that time to renew these conditions. Of specific public interest, one condition that is included with the Environmental Compliance Approval with Limited Operational Flexibility (air & noise) requires the company to make available, at all times, at the facility for inspection by interested members of the Public, a table (emission summary table) that documents the facility’s compliance with Ontario Regulation 419/05.
Supporting materials
View materials in person
Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.
Get in touch with the office listed below to find out if materials are available.
40 St. Clair Avenue West
Floor 2
Toronto,
ON
M4V 1M2
Canada
How to Appeal
This instrument decision can be appealed. You have 15 days from June 17, 2026 to begin the appeal process.
Carefully review the information below to learn more about the appeal process.
How to appealClick to Expand Accordion
Start the process to appeal
If you’re an Ontario resident, you can start the process to appeal this instrument decision.
First, you’ll need to seek leave (i.e. get permission) from the relevant appellate body to appeal the decision.
If the appellate body grants leave, the appeal itself will follow.
Seek leave to appeal
To seek leave to appeal, you need to do these three things:
- prepare your application
- provide notice to the minister
- mail your application to three parties
1. Prepare your application
You’ll need to prepare an application. You may wish to include the following things in your application:
- A document that includes:
- your name, phone number, fax number (if any), and/or email address
- the ERO number and ministry reference number (located on this page)
- a statement about whether you are a resident in Ontario
- your interest in the decision, and any facts you want taken into account in deciding whether you have an interest in the decision
- the parts of the instrument that you’re challenging
- whether the decision could result in significant harm to the environment
- the reason(s) why you believe that no reasonable person – having regard to the relevant law and to any government policies developed to guide decisions of that kind – could have made the decision
- the grounds (facts) you’ll be using to appeal
- the outcome you’d like to see
- A copy of the instrument (approval, permit, order) that you you are seeking leave to appeal. You’ll find this in the decision notice on the Environmental Registry
- Copies of all supporting documents, facts and evidence that you’ll be using to appeal
What is considered
The appeal body will consider the following two questions in deciding whether to grant you leave to appeal:
- is there is good reason to believe that no reasonable person, with respect to the relevant law and to any government policies developed to guide decisions of that kind, could have made the decision?
- could the decision you wish to appeal result in significant harm to the environment?
2. Provide your notice
You’ll need to provide notice to the Minister of the Environment, Conservation and Parks that you’re seeking leave to appeal.
In your notice, please include a brief description of the:
- decision that you wish to appeal
- grounds for granting leave to appeal
You can provide notice by email at minister.mecp@ontario.ca or by mail at:
College Park 5th Floor, 777 Bay St.
Toronto, ON
M7A 2J3
3. Mail your application
You’ll need to mail your application that you prepared in step #1 to each of these three parties:
- appellate body
- issuing authority (the ministry official who issued the instrument)
- proponent (the company or individual to whom the instrument was issued)
NUCOR STEEL ULC
5400 Harvester Road
Burlington,
ON
L7L 5N5
Canada
Registrar, Ontario Land Tribunal
655 Bay Street, Suite 1500
Toronto, Ontario
M5G 1E5
(416) 212-6349
(866) 448-2248
OLT.Registrar@ontario.ca
Include the following:
This is not legal advice. Please refer to the Environmental Bill of Rights for exact legal requirements. Consult a lawyer if you need help with the appeal process.
Connect with us
Contact
Client Services and Permissions Branch
40 St. Clair Avenue West
Floor 2
Toronto,
ON
M4V 1M2
Canada
Original proposal
Proposal details
This proposal is for the renewal of the Limited Operational Flexibility for an Environmental Compliance Approval (air & noise) No. 9602-A5WQQK for Nucor Steel ULC, a facility that manufacturers low-carbon free-machined cold-finished bar products and wire mesh, located in the City of Burlington, Ontario. The emission sources from the manufacturing and associated processes that discharge to the air include coil blasting, drawing machines, teurema line, galvanizing line, mesh line, mesh fabrication, exhaust stacks from dust collectors, general building roof vents and exhaust fans, cooling towers, boilers and emergency generators. Emissions to the air from this facility include:
- iron oxide
- lead
- manganese
- nickel
- nitrogen oxides
- suspended particulate matter
- noise
The Environmental Compliance Approval with Limited Operational Flexibility (air & noise), when issued, permits modifications to the facility subject to limits on operational flexibility that include a production limit for the facility to be specified on the Environmental Compliance Approval with Limited Operational Flexibility (air & noise). The limited operational flexibility conditions have an expiry date. The company will be required to make an application for amendment at that time to renew these conditions.
Supporting materials
View materials in person
Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.
Get in touch with the office listed below to find out if materials are available.
40 St. Clair Avenue West
Floor 2
Toronto,
ON
M4V 1M2
Canada
Comment
Commenting is now closed.
This consultation was open from May 20, 2025
to July 4, 2025
Connect with us
Contact
Client Services and Permissions Branch
40 St. Clair Avenue West
Floor 2
Toronto,
ON
M4V 1M2
Canada
Comments received
Through the registry
0By email
0By mail
0