The Director of Exploration has made a decision on the exploration permit application PR-20-000100 to Battery Mineral Resources Limited for early exploration activities near Matachewan, Ontario. The decision is to: Issue
The Ministry of Infrastructure has updated its Statement of Environmental Values to reflect the changes in its structure and mandate, as well as to acknowledge the priority of addressing climate change.
November 25, 2025 - January 9, 2026 (45 days) Closed
Last updated
An Environmental Compliance Approval is granted to Southview Hydrovac Inc. to operate a liquid excess soil processing facility at 144 North Port Road, Port Perry (Township of Scugog) Ontario.
We have received a notice of material changes for Vale Canada Limited Copper Cliff North Mine, Clarabelle Mill and Copper Cliff Central Tailings Area Operations that will result in Vale Canada Limited submitting closure plan amendments.
We approved an amendment to the Environmental Compliance Approval (a waste disposal site) No. A220249 issued to Safety-Kleen Canada Inc., for the addition of new waste types, waste processing activities and waste storage areas to the facility located at 25 Regan Road in Brampton, Ontario.
October 18, 2024 - November 21, 2024 (34 days) Closed
Last updated
Ontario has made amendments to Ontario Regulation 406/19 to enable greater reuse of excess soil, provide added flexibility in soil management options, and reduce costs for businesses. This is an update to our previous December 2024 decision notice regarding a change to the in-effect date of a provision to restrict landfilling of cleaner excess soil
Instrument type:
Permit for activities to achieve an overall benefit to a species
ERO number
019-4975
Notice type
Instrument
Notice stage
Decision
Decision posted
Proposal posted
Comment period
September 6, 2022 - October 6, 2022 (30 days) Closed
Last updated
The minister has issued an overall benefit permit to the Regional Municipality of Halton to carry out improvements to Dundas Street West, which will impact Redside Dace, a species at risk fish. The permit includes actions to benefit the species and minimize adverse effects, and outlines monitoring and reporting requirements.
December 19, 2024 - January 18, 2025 (30 days) Closed
Last updated
We are seeking public input on what actions Ontario should take, if any, in response to the results of the "Cumulative Impact Assessment of Withdrawals, Consumptive Uses and Diversions: 2016-2020” conducted under the Great Lakes-St. Lawrence River Basin Sustainable Water Resources Agreement.
September 12, 2025 - October 27, 2025 (45 days) Closed
Last updated
The decision is for a new Environmental Compliance Approval for the establishment of an onsite Class 4 sewage works servicing a proposed warehousing development at 128 Brock Road South in the Township of Puslinch, Ontario.
December 15, 2023 - January 29, 2024 (45 days) Closed
Last updated
Porcelain Technologies Limited requested to withdraw their application for an Environmental Compliance Approval. The application is considered withdrawn and no approval was issued.
August 30, 2018 - October 14, 2018 (45 days) Closed
Last updated
An amendment to Environmental Compliance Approval (Air & Noise) No. 0406-AF4LH6 has been issued to R. W. Tomlinson Limited, a facility used for quarrying and processing of aggregate materials, located in the Town of Bruce Mines, Ontario.
January 31, 2019 - March 17, 2019 (45 days) Closed
Last updated
An amended Environmental Compliance Approval with limited operational flexibility has been issued to all sources of air emissions from the D. Crupi & Sons Limited facility located at 1089 Nelson Street in Oshawa.
December 4, 2023 - January 18, 2024 (45 days) Closed
Last updated
Environmental Compliance Approval number 0992-D68QGF was issued to Roelands Plant Farms Inc. for the establishment of stormwater management works in support of a proposed greenhouse and bunkhouse development, for the collection, transmission, treatment and disposal of stormwater run-off.