WATER TAKINGS • Please…

ERO number

019-6853

Comment ID

94325

Commenting on behalf of

Stantec Consulting Ltd.

Comment status

Comment approved More about comment statuses

Comment

WATER TAKINGS
• Please clarify the following requirement provided under Applicable Requirements under O.Reg. 63/16 for Construction Site Dewatering
o Specific criteria must be met when discharging water taken during the construction project:
-Any ground water or storm water discharged to land or a storm sewer that is within 30 metres of a water body shall ensure that the turbidity of the discharge does not exceed 8 Nephelometric Turbidity Units (NTU) above the background level of the nearest water body