SNC-Lavalin Trillium Partner 1 Inc. and SNC-Lavalin Trillium Partner 2 Inc. operating as TransitNEXT General Partnership

La traduction française de cet avis n'est pas disponible. Nous nous excusons pour le dérangement.

Numéro du REO
019-3662
Type d'avis
Bulletin
Loi
Ontario Water Resources Act, R.S.O. 1990
Affiché par
Ministry of the Environment, Conservation and Parks
Date d’affichage
Dernière mise à jour

Le présent avis est fourni à titre d’information seulement. Il n’existe aucune obligation de mener une consultation sur le Registre environnemental de l’Ontario à propos de cette initiative. Pour en savoir davantage sur le processus de consultation et les types d’avis publiés sur le registre.

Résumé de l’avis

A new PTTW P-300-7087157725 has been issued to SNC-Lavalin Trillium Partner 1 Inc. and SNC-Lavalin Trillium Partner 2 Inc. operating as TransitNEXT General Partnership on August 28, 2020 for dewatering purposes located in the City of Ottawa, Ontario. The new Permit to Take Water has an expiry date of August 31, 2022.

Pourquoi une consultation n’est pas nécessaire

On April 1, 2020, the Ontario Government made a temporary regulation to respond to the COVID-19 outbreak. Ontario Regulation 115/20 exempted all proposals for policies, acts, regulations and instruments from posting requirements under the EBR.

Ontario Regulation 115/20 was revoked on June 15, 2020, however, we are posting this decision as a bulletin as because the proposal was posted on May 8, 2020 while Ontario Regulation 115/20 was in effect.

Although consultation was not required, the ministry did consulted with the public on this proposal by posting ERO# 019-1757 for public comment from May 8, 2020 - June 7, 2020. To ensure transparency, the ministry is providing details of its decision and the effects of consultation on decision-making in this notice.

Détails

Proponent

SNC-Lavalin Trillium Partner 1 Inc. and SNC-Lavalin Trillium Partner 2 Inc. operating as TransitNEXT General Partnership
1145 Hunt Club Road
Suite 300
Ottawa, Ontario
K1V 0Y3
Canada

Location details

Bowesville Station, Earl Armstrong Bridge, and Bowesville Bridge
Ottawa, Ontario
K1X 1B3
Canada

Instrument decision

A new PTTW P-300-7087157725 has been issued to SNC-Lavalin Trillium Partner 1 Inc. and SNC-Lavalin Trillium Partner 2 Inc. operating as TransitNEXT General Partnership on August 28, 2020 for dewatering purposes located in the City of Ottawa, Ontario. The new Permit to Take water has an expiry date of August 31, 2022.

Water will be taken from three (3) wells related to construction activities, located in the City of Ottawa, Ontario. Details of water taking are as follows:

Permit type - new (Category 3)

Source 1

  • purpose of water taking: dewatering - construction
  • source of water: well - drilled
  • maximum rate (litres per minute): 2,417
  • maximum number of hours of taking per day: 24
  • maximum volume (litres) per day: 3,480,000
  • maximum number of days of taking in a tear: 365
  • earliest calendar date of taking (mm/dd): 01/01
  • latest calendar date of taking (mm/dd): 12/31
  • period of water taking: 2 years

Source 2

  • purpose of water taking: dewatering - construction
  • source of water: well - drilled
  • maximum rate (litres per minute): 861
  • maximum number of hours of taking per day: 24
  • maximum volume (litres) per day: 1,240,000
  • maximum number of days of taking in a year: 365
  • earliest calendar date of taking (mm/dd): 01/01
  • latest calendar date of taking (mm/dd): 12/31
  • period of water taking: 2 years

Source 3

  • purpose of water taking: dewatering - construction
  • source of water: well - drilled
  • maximum rate (litres per minute): 1,075
  • maximum number of hours of taking per day: 24
  • maximum volume (litres) per day: 1,548,000
  • maximum number of days of taking in a year: 365
  • earliest calendar date of taking (mm/dd): 01/01
  • latest calendar date of taking (mm/dd): 12/31
  • period of water taking: 2 years

Request a copy of the permit

Comments received

One comment was received.

Effects of consultation

The comment was off topic, there is no impact of comment on the approval.

Third parties are not able to apply for leave to appeal in respect of proposals which were posted while Ontario Regulation 115/20 was in effect between April 1, 2020 and June 14, 2020. Ontario Regulation 115/20 exempted all proposals for instruments from posting requirements under the EBR. Leave to appeal may only be sought in respect of instruments that are required to be posted to the ERO.

Appeals information

Appeals are not allowed. This instrument type cannot be appealed.

Documents justificatifs

Consulter les documents en personne

Certains documents justificatifs peuvent ne pas être accessibles en ligne. Si tel est le cas, vous pouvez demander à consulter les documents en personne.

Veuillez communiquer avec le bureau mentionné ci-dessous pour savoir si les documents sont accessibles.

Communiquer avec nous

Contact

S'inscrire pour obtenir des avis

Nous vous enverrons des avis par courriel accompagnés de toute mise à jour liée à cette consultation. Vous pouvez modifier vos préférences relatives à l'avis en tout temps en allant à votre page de profil où se trouvent vos paramètres.

Suivre cet avis