Goldcorp Canada Ltd. Instrument type: Permit to take water

ERO number
019-2314
Notice type
Bulletin
Act
Ontario Water Resources Act, R.S.O. 1990
Posted by
Ministry of the Environment, Conservation and Parks
Bulletin posted
Last updated

This notice is for informational purposes only. There is no requirement to consult on this initiative on the Environmental Registry of Ontario. Learn more about the types of notices on the registry.

Bulletin summary

We have renewed Permit To Take Water Number No. 7727–88EHF7 for industrial purposes for Goldcorp Canada Ltd., located at the Musselwhite Mine, approximately 130 kilometres north of the town of Pickle Lake and approximately 470 kilometres northwest of Thunder Bay.

Why consultation isn't required

On April 1, 2020, the Ontario Government made a temporary regulation to respond to the COVID-19 outbreak. Ontario Regulation 115/20 exempted all proposals for policies, acts, regulations and instruments from posting requirements under the EBR.

Ontario Regulation 115/20 was revoked on June 15, 2020, however, we are posting this decision as a bulletin as because the proposal was posted on April 28, 2020 while Ontario Regulation 115/20 was in effect.

Although consultation was not required, the ministry did consulted with the public on this proposal by posting ERO# 019-1710 for public comment from April 28, 2020 - May 28, 2020. To ensure transparency, the ministry is providing details of its decision and the effects of consultation on decision-making in this notice.

Bulletin details

Location details:

District of Kenora, ON

Canada

Site location details:

Musselwhite Mine Cement Fill Plant

Approximately 130 kilometres north of the town of Pickle Lake and 470 kilometres northwest of Thunder BayUnsurveyed Territory, Unorganized Area, District of Kenora

Proponent(s)

Goldcorp Canada Ltd.
P.O. Box 7500
Station P
Thunder Bay, ON
P7B 6S8
Canada

Decision Details:

Permit To Take Water Number No. 7727–88EHF7 was renewed and issued to Goldcorp Canada Ltd. for industrial purposes. Water will be taken from two (2) wells for the operation of a Cement Rock Fill Plant at the Musselwhite Mine, located approximately 130 kilometres north of the town of Pickle Lake and approximately 470 kilometres northwest of Thunder Bay.

Details of the water taking are as follows:

Source of water: well (CFP-PW1)

  • purpose of taking: industrial - cement backfill
  • maximum rate per minute (litres): 450
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 650,000
  • maximum number of days of taking per year: 365
  • period of taking: January 1 to December 31 for 10 years

Source of water: well (CFP-PW2)

  • purpose of taking: industrial - cement backfill
  • maximum rate per minute (litres): 450
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 650,000
  • maximum number of days of taking per year: 365
  • period of taking: January 1 to December 31 for 10 years

Comment Received:

  • 1 comment was received through the registry
  • 0 comments were received by mail
  • 0 comments were received by email

Effects of Consulation:

The comment received identified concern with the posting under Ontario Regulation 115/20. The comment was considered, and information on why consultation isn't required is provided in the above section.

Third parties are not able to apply for leave to appeal in respect of proposals which are posted while Ontario Regulation 115/20 is in effect. On April 1, 2020, the Ontario Government made a temporary regulation to respond to the COVID-19 outbreak which exempts all proposals from the requirement to post notices on the ERO. Leave to appeal may only be sought in respect of instruments that are required to be posted to the ERO.

Appeal Information:

This instrument type cannot be appealed.

Supporting materials

View materials in person

Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.

Get in touch with the office listed below to find out if materials are available.

Connect with us

Contact

Sign up for notifications

We will send you email notifications with any updates related to this consultation. You can change your notification preferences anytime by visiting settings in your profile page.

Follow this notice