This notice is for informational purposes only. There is no requirement to consult on this initiative on the Environmental Registry of Ontario. Learn more about the types of notices on the registry.
Why consultation isn't required
On April 1, 2020, the Ontario Government made a temporary regulation to respond to the COVID-19 outbreak. Ontario Regulation 115/20 exempts all proposals for policies, acts, regulations and instruments from posting requirements under the EBR.
Ontario Regulation 115/20 was revoked on June 15, 2020, however, we are posting this decision as a bulletin because the proposal was posted on original posting date, while Ontario Regulation 115/20 was in effect.
Although consultation was not required, the ministry did consult with the public on this proposal by posting ERO # 019-1588 for public comment from April 2, 2020 to May 17, 2020. To ensure transparency, the ministry is providing details of its decision and the effects of consultation on decision-making in this notice.
Bulletin details
Proponent
Remicorp Industries Inc.
545 Commissioners Street
Toronto, Ontario
M4M 1A5
Location details
545 Commissioners Street
Toronto, Ontario
M4M 1A5
To see the site location on a map, please refer to the instrument proposal under ERO # 019-1588.
Instrument decision
An Environmental Compliance Approval (air) has been granted to Remicorp Industries Inc., a ready-mix concrete batching plant and aggregate retail operation located in the City of Toronto, Ontario.
This approval includes all emission sources from the facility that exhaust to the atmosphere, including:
- five baghouse dust collectors
- two natural gas fired water heaters
- one natural gas fired boiler
- fugitive emissions from the delivery, storage, transfer, and handling of materials associated with the ready-mix concrete batching and aggregate retail operations
Contaminant emissions to the atmosphere include particulate matter, portland cement, slag, fly ash, and nitrogen oxides.
Comments received
No comments were received.
Effects of consultation
Since we did not receive any comment during the commenting period, there is no impact of comment on the approval.
Third parties are not able to apply for leave to appeal in respect of proposals which were posted while Ontario Regulation 115/20 was in effect between April 1, 2020 and June 14, 2020. Ontario Regulation 115/20 exempted all proposals for instruments from posting requirements under the EBR. Leave to appeal may only be sought in respect of instruments that are required to be posted to the ERO.
Appeals information
Appeals are not allowed. This instrument type cannot be appealed.
Supporting materials
View materials in person
Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.
Get in touch with the office listed below to find out if materials are available.
Connect with us
Contact
Client Services and Permissions Branch
135 St Clair Ave West
1st Floor
Toronto,
ON
M4V 1P5
Canada