Proposal summary
This proposal is for a renewal of Permit to Take Water No. 1213-933SR9 for mining, dewatering and water supply purposes. Water will be taken from one lake, two ponds and two wells at the Kearney Mine, located in Kearney, Ontario.
Location details
Site address
2142 Forestry Tower Road
Kearney,
ON
Canada
Site location map
The location pin reflects the approximate area where environmental activity is taking place.
View this location on a map opens link in a new windowProponent(s)
Ontario Graphite, Ltd.
2142 Forestry Tower Road
Kearney,
ON
P0A 1M0
Canada
Proposal details
This proposal is for a renewal of Permit to Take Water No. 1213-933SR9 for mining, dewatering and water supply purposes. Water will be taken from one lake, two ponds and two wells at the Kearney Mine, located in Kearney, Ontario. Details of the water taking are as follows:
Source name: Graphite Lake
- purpose of taking: mining
- paximum rate per minute (litres): 4,167
- paximum number of hours of taking per day: 24
- paximum volume per day (litres): 6,000,000
- paximum number of days of taking per year: 365
- period of taking: January 1 to December 31 for 10 years
Source name: Polishing Pond
- purpose of taking: mining
- maximum rate per minute (litres): 512
- maximum number of hours of taking per day: 24
- maximum volume per day (litres): 737,000
- maximum number of days of taking per year: 365
- period of taking: January 1 to December 31 for 10 years
Source name: Unnamed Creek Reporting to Polishing Pond
- purpose of taking: construction dewatering
- maximum rate per minute (litres): 4,167
- maximum number of hours of taking per day: 24
- maximum volume per day (litres): 6,000,000
- maximum number of days of taking per year: 365
- period of taking: January 1 to December 31 for 10 years
Source name: Unnamed Creek Reporting to Polishing Pond
- purpose of taking: water supply
- maximum rate per minute (litres): 9,028
- maximum number of hours of taking per day: 24
- maximum volume per day (litres): 13,000,000
- maximum number of days of taking per year: 92
- period of taking: January 1 to December 31 for 10 years
Source name: Unnamed Creek Reporting to Polishing Pond
- purpose of taking: water supply
- maximum rate per minute (litres): 6,944
- maximum number of hours of taking per day: 24
- maximum volume per day (litres): 10,000,000
- maximum number of days of taking per year: 61
- period of taking: January 1 to December 31 for 10 years
Source name: Open Pit
- purpose of taking: dewatering
- maximum rate per minute (litres): 2,778
- maximum number of hours of taking per day: 24
- maximum volume per day (litres): 4,000,000
- maximum number of days of taking per year: 365
- period of taking: January 1 to December 31 for 10 years
Source name: Mill Yard Cut-Off Trench
- purpose of taking: mining
- maximum rate per minute (litres): 1,910
- maximum number of hours of taking per day: 24
- maximum volume per day (litres): 2,750,000
- maximum number of days of taking per year: 365
- period of taking: January 1 to December 31 for 10 years
Source name: Mill Yard Cut-Off Trench
- purpose of taking: construction dewatering
- maximum rate per minute (litres): 960
- maximum number of hours of taking per day: 24
- maximum volume per day (litres): 1,382,000
- maximum number of days of taking per year: 61
- period of taking: January 1 to December 31 for 10 years
There are 3 categories of a Permit to Take Water:
- Category 1: water takings are anticipated to have a lower risk of causing an unacceptable environmental impact/interference
- Category 2: water takings are anticipated to having a higher potential of causing unacceptable environmental impact or interference
- Category 3: water takings are anticipated to have the highest potential of causing unacceptable environmental impactor interference
The proposed water taking qualifies as a Category 1 permit.
Supporting materials
View materials in person
Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.
Get in touch with the office listed below to find out if materials are available.
135 St. Clair Avenue West
Floor 1
Toronto,
ON
M4V 1P5
Canada
Connect with us
Contact
Client Services and Permissions Branch
135 St Clair Ave West
1st Floor
Toronto,
ON
M4V 1P5
Canada
Comment
Commenting is now closed.
The comment period was from May 2, 2023
to June 1, 2023