Proposal summary
This proposal is for a new Environmental Compliance Approval (sewage) for Miller Paving Limited to establish stormwater management works to service a proposed industrial manufacturing plant, located at 175 Bethridge Road, in the City of Toronto, Ontario.
Location details
Site address
175 Bethridge Road
Toronto,
ON
Canada
Site location map
The location pin reflects the approximate area where environmental activity is taking place.
View this location on a map opens link in a new windowProponent(s)
Miller Paving Limited
281 Hillmount Road
Suite 101
Markham,
ON
L6C 2S3
Canada
Proposal details
This proposal is for a new Environmental Compliance Approval (sewage) for Miller Paving Limited to establish stormwater management works to service a proposed industrial manufacturing plant for collection, transmission, treatment and disposal of stormwater run-off from the lands located at 175 Bethridge Road, in the City of Toronto, Ontario.
The proposed stormwater management works include an underground storage tank, complete with storm sewers. Runoff generated on the site will be captured through a series of double catch basins and conveyed through 200-525 millimetre diameter storm sewers into a stormwater facility before ultimately discharging to the existing 600 millimetre culvert at the southeast corner of the site.
Storage is provided within the stormwater facility, proposed pipes and the structures for storm events up to the 100-year. Stormwater from the Site will be attenuated though an orifice tube into the Jellyfish Filter, and then discharged to the existing 600 millimetre culvert. Furthermore, stormwater runoff generated from the plant’s operation area, where there is potential contamination, will be conveyed overland to the water recycle facility.
The flows up to the major (100-year) storm event generated in the operation area will be contained/stored in the compartment of the water recycle facility and will be pumped back to the plant to be re-used for the plant operations. The grading and servicing have been designed in this manner to avoid discharging any contaminated stormwater off site.
Supporting materials
View materials in person
Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.
Get in touch with the office listed below to find out if materials are available.
135 St Clair Ave West
1st Floor
Toronto,
ON
M4V 1P5
Canada
Connect with us
Contact
Client Services and Permissions Branch
135 St Clair Ave West
1st Floor
Toronto,
ON
M4V 1P5
Canada
Comment
Commenting is now closed.
The comment period was from August 9, 2024
to September 23, 2024