This consultation was open from:
October 29, 2024
to December 13, 2024
Decision summary
This approval is for a new Environmental Compliance Approval (M&P sewage) for stormwater management works serving the Truly Green Farms Greenhouse development site, located at 162 Bloomfield Road located in Chatham, Ontario.
This application is for a new wet pond stormwater management facility, discharging to surface waters via Lake St. Clair.
Location details
Site address
162 Bloomfield Road
Chatham,
ON
Canada
Site location map
The location pin reflects the approximate area where environmental activity is taking place.
View this location on a map opens link in a new windowProponent(s)
Truly Green Farms Ltd.
162 Bloomfield Road
Chatham,
ON
N7M 0R4
Canada
Decision details
This approval is for a new Environmental Compliance Approval (M&P sewage) for stormwater management works serving the Truly Green Farms Greenhouse development site, located at 162 Bloomfield Road located in Chatham, Ontario.
This application is for a new wet pond stormwater management facility, discharging to surface waters via Lake St. Clair. The stormwater management works consist of the following:
- roof water drainage pipe systems, swales, and on-site storm sewers, discharging roof top runoff and other surface runoff to stormwater detention pond
- one stormwater management detention/wet pond having an active storage volume of 13,260.9 cubic metres with a maximum active water depth of 2.26 metres for the 1:100-year storm event, discharging a maximum total release rate of 418 litres per second into the Payne and Backus Drain
- one irrigation/stormwater management reservoir is designed to be built in the future. It will collect roof water and be used for irrigation purposes of the crops
- one emergency overflow spillway directed to the Payne and Backus Drain
- one outlet structure containing a 375 millimetres diametres outlet pipe, flap gate and containment valve
Effects of consultation
No comments were received during the posting period of 45 days.
Supporting materials
View materials in person
Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.
Get in touch with the office listed below to find out if materials are available.
135 St Clair Ave West
1st Floor
Toronto,
ON
M4V 1P5
Canada
How to Appeal
This instrument decision can be appealed. You have 15 days from June 1, 2026 to begin the appeal process.
Carefully review the information below to learn more about the appeal process.
How to appealClick to Expand Accordion
Start the process to appeal
If you’re an Ontario resident, you can start the process to appeal this instrument decision.
First, you’ll need to seek leave (i.e. get permission) from the relevant appellate body to appeal the decision.
If the appellate body grants leave, the appeal itself will follow.
Seek leave to appeal
To seek leave to appeal, you need to do these three things:
- prepare your application
- provide notice to the minister
- mail your application to three parties
1. Prepare your application
You’ll need to prepare an application. You may wish to include the following things in your application:
- A document that includes:
- your name, phone number, fax number (if any), and/or email address
- the ERO number and ministry reference number (located on this page)
- a statement about whether you are a resident in Ontario
- your interest in the decision, and any facts you want taken into account in deciding whether you have an interest in the decision
- the parts of the instrument that you’re challenging
- whether the decision could result in significant harm to the environment
- the reason(s) why you believe that no reasonable person – having regard to the relevant law and to any government policies developed to guide decisions of that kind – could have made the decision
- the grounds (facts) you’ll be using to appeal
- the outcome you’d like to see
- A copy of the instrument (approval, permit, order) that you you are seeking leave to appeal. You’ll find this in the decision notice on the Environmental Registry
- Copies of all supporting documents, facts and evidence that you’ll be using to appeal
What is considered
The appeal body will consider the following two questions in deciding whether to grant you leave to appeal:
- is there is good reason to believe that no reasonable person, with respect to the relevant law and to any government policies developed to guide decisions of that kind, could have made the decision?
- could the decision you wish to appeal result in significant harm to the environment?
2. Provide your notice
You’ll need to provide notice to the Minister of the Environment, Conservation and Parks that you’re seeking leave to appeal.
In your notice, please include a brief description of the:
- decision that you wish to appeal
- grounds for granting leave to appeal
You can provide notice by email at minister.mecp@ontario.ca or by mail at:
College Park 5th Floor, 777 Bay St.
Toronto, ON
M7A 2J3
3. Mail your application
You’ll need to mail your application that you prepared in step #1 to each of these three parties:
- appellate body
- issuing authority (the ministry official who issued the instrument)
- proponent (the company or individual to whom the instrument was issued)
Truly Green Farms Ltd.
162 Bloomfield Road
Chatham,
ON
N7M 0R4
Canada
Registrar, Ontario Land Tribunal
655 Bay Street, Suite 1500
Toronto, Ontario
M5G 1E5
(416) 212-6349
(866) 448-2248
OLT.Registrar@ontario.ca
Include the following:
This is not legal advice. Please refer to the Environmental Bill of Rights for exact legal requirements. Consult a lawyer if you need help with the appeal process.
Connect with us
Contact
Client Services and Permissions Branch
135 St Clair Ave West
1st Floor
Toronto,
ON
M4V 1P5
Canada
Original proposal
Proposal details
This proposal is for a new Environmental Compliance Approval (M&P sewage) for stormwater management works serving the Truly Green Farms Greenhouse development site, located at 162 Bloomfield Road located in Chatham, Ontario.
This application is for a new wet pond stormwater management facility, discharging to surface waters via Lake St. Clair. The stormwater management works consist of the following:
- roof water drainage pipe systems, swales, and on-site storm sewers, discharging roof top runoff and other surface runoff to stormwater detention pond;
- one stormwater management detention/wet pond having an active storage volume of 13,260.9 cubic metres with a maximum active water depth of 2.26 metres for the 1:100-year storm event, discharging a maximum total release rate of 418 litres per second into the Payne and Backus Drain;
- one irrigation/stormwater management reservoir is designed to be built in the future. It will collect roof water and be used for irrigation purposes of the crops;
- one emergency overflow spillway directed to the Payne and Backus Drain;
- one outlet structure containing a 375 millimetres diametres outlet pipe, flap gate and containment valve.
Supporting materials
View materials in person
Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.
Get in touch with the office listed below to find out if materials are available.
135 St Clair Ave West
1st Floor
Toronto,
ON
M4V 1P5
Canada
Comment
Commenting is now closed.
This consultation was open from October 29, 2024
to December 13, 2024
Connect with us
Contact
Client Services and Permissions Branch
135 St Clair Ave West
1st Floor
Toronto,
ON
M4V 1P5
Canada
Comments received
Through the registry
0By email
0By mail
0