Waste Management of Canada Corporation - Permit to take water

Instrument type: Permit to take water

ERO number
025-0141
Ministry reference number
0853-DDEK8X
Notice type
Instrument
Act
Ontario Water Resources Act, R.S.O. 1990
Posted by
Ministry of the Environment, Conservation and Parks
Notice stage
Proposal
Proposal posted
Comment period
March 10, 2025 - April 9, 2025 (30 days) Open
Last updated

This consultation closes at 11:59 p.m. on:
April 9, 2025

Proposal summary

This proposal is for a renewal and consolidation of Permits to Take Water No. 0204-9UCSW6 & 5547-9UCQ26 for Waste Management of Canada Corporation. Water will be taken from two wells and four ponds for various purposes related to the operation of the on-site landfill, located in the City of Ottawa, Ontario.

Location details

Site address

2301 Carp Road
Ottawa, ON
Canada

Site location details

Lots 3, 4 and 5, Concession III, Geographic Township of Huntley

Site location map

The location pin reflects the approximate area where environmental activity is taking place.

View this location on a map opens link in a new window

Proponent(s)

Waste Management of Canada Corporation
2301 Carp Road
Ottawa, ON
K0A 1L0
Canada

Proposal details

This proposal is for a renewal and consolidation of Permits No. 0204-9UCSW6 & 5547-9UCQ26 for Waste Management of Canada Corporation. Water will be taken from two wells and four ponds for various purposes related to the operation of the on-site landfill, located in the City of Ottawa, Ontario. Details of the water taking are as follows:

Permit type – renewal and consolidation

Source Name: Stormwater Pond 1

  • purpose: miscellaneous (various on-Site usage)
  • maximum rate per minute (litres): 2,400
  • maximum number of hours of taking per day: 10
  • maximum volume per day (litres): 62,500
  • maximum number of days of taking per year: 240
  • earliest calendar date of taking (mm/dd): 04/01
  • latest calendar date of taking (mm/dd): 12/01
  • period of taking: 10 years

Source Name: Stormwater Pond 2

  • purpose: miscellaneous (various on-Site usage)
  • maximum rate per minute (litres): 2,400
  • maximum number of hours of taking per day: 10
  • maximum volume per day (litres): 105,000
  • maximum number of days of taking per year: 240
  • earliest calendar date of taking (mm/dd): 04/01
  • latest calendar date of taking (mm/dd): 12/01
  • period of taking: 10 years

Source Name: CD (excavation)

  • purpose: construction dewatering
  • maximum rate per minute (litres): 2,400
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 3,456,000
  • maximum number of days of taking per year: 365
  • earliest calendar date of taking (mm/dd): 01/01
  • latest calendar date of taking (mm/dd): 12/31
  • period of taking: 10 years

Source Name: SDL (pumping station)

  • purpose: construction dewatering
  • maximum rate per minute (litres): 900
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 1,296,000
  • maximum number of days of taking per year: 365
  • earliest calendar date of taking (mm/dd): 01/01
  • latest calendar date of taking (mm/dd): 12/31
  • period of taking: 10 years

Source Name: Purge Well System (wells PW1-PW10, PW20, PW26, PW27, PW30)

  • purpose: groundwater remediation
  • maximum rate per minute (litres): 1,421
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 2,045,700
  • maximum number of days of taking per year: 365
  • earliest calendar date of taking (mm/dd): 01/01
  • latest calendar date of taking (mm/dd): 12/31
  • period of taking: 10 years

Source Name: Pond (Dust)

  • purpose: miscellaneous (various on-site usage)
  • maximum rate per minute (litres): 42
  • maximum number of hours of taking per day: 10
  • maximum volume per day (litres): 25,000
  • maximum number of days of taking per year: 150
  • earliest calendar date of taking (mm/dd): 01/01
  • latest calendar date of taking (mm/dd): 12/31
  • period of taking: 10 years

Source Name: Pond (Poplar)

  • purpose: miscellaneous (various on-site usage)
  • maximum rate per minute (litres): 583
  • maximum number of hours of taking per day: 10
  • maximum volume per day (litres): 350,000
  • maximum number of days of taking per year: 200
  • earliest calendar date of taking (mm/dd): 01/01
  • latest calendar date of taking (mm/dd): 12/31
  • period of taking: 10 years

Source Name: Pond (Other)

  • purpose: miscellaneous (various on-site usage)
  • maximum rate per minute (litres): 52
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 75,000
  • maximum number of days of taking per year: 365
  • earliest calendar date of taking (mm/dd): 01/01
  • latest calendar date of taking (mm/dd): 12/31
  • period of taking: 10 years

There are 3 categories of a Permit to Take Water:

  • Category 1: water takings are anticipated to have a lower risk of causing an unacceptable environmental impact/interference
  • Category 2: water takings are anticipated to having a higher potential of causing unacceptable environmental impact or interference
  • Category 3: water takings are anticipated to have the highest potential of causing unacceptable environmental impactor interference

    The proposed water taking qualifies as a Category 1 permit.

    Supporting materials

    View materials in person

    Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.

    Get in touch with the office listed below to find out if materials are available.

    Client Services and Permissions Branch
    Address

    135 St Clair Ave West
    1st Floor
    Toronto, ON
    M4V 1P5
    Canada

    Office phone number

    Comment

    Let us know what you think of our proposal.

    Have questions? Get in touch with the contact person below. Please include the ERO number for this notice in your email or letter to the contact.

    Read our commenting and privacy policies.

    Submit online

    Submit by mail

    Contact

    Connect with us

    Contact

    Sign up for notifications

    We will send you email notifications with any updates related to this consultation. You can change your notification preferences anytime by visiting settings in your profile page.

    Follow this notice