Waste Management of Canada Corporation - Permit to take water

La traduction française de cet avis n'est pas disponible. Nous nous excusons pour le dérangement.

Type d'acte: Permit to take water

Numéro du REO
025-0141
Numéro de référence du ministère
0853-DDEK8X
Type d'avis
Instrument
Loi
Ontario Water Resources Act, R.S.O. 1990
Affiché par
Ministry of the Environment, Conservation and Parks
Étape de l'avis
Proposition
Proposition affichée
Période de consultation
Du 10 mars 2025 au 9 avril 2025 (30 jours) Fermé
Dernière mise à jour

Cette consultation a eu lieu :

du 10 mars 2025
au 9 avril 2025

Résumé de la proposition

This proposal is for a renewal and consolidation of Permits to Take Water No. 0204-9UCSW6 & 5547-9UCQ26 for Waste Management of Canada Corporation. Water will be taken from two wells and four ponds for various purposes related to the operation of the on-site landfill, located in the City of Ottawa, Ontario.

Détails de l'emplacement

Adresse du site

2301 Carp Road
Ottawa, ON
Canada

Détails de l'emplacement du site

Lots 3, 4 and 5, Concession III, Geographic Township of Huntley

Carte de l'emplacement du site

L'épingle de localisation correspond à la zone approximative où a lieu l’activité environnementale.

Afficher cet emplacement sur une carte opens link in a new window

Promoteur(s)

Waste Management of Canada Corporation
2301 Carp Road
Ottawa, ON
K0A 1L0
Canada

Détails de la proposition

This proposal is for a renewal and consolidation of Permits No. 0204-9UCSW6 & 5547-9UCQ26 for Waste Management of Canada Corporation. Water will be taken from two wells and four ponds for various purposes related to the operation of the on-site landfill, located in the City of Ottawa, Ontario. Details of the water taking are as follows:

Permit type – renewal and consolidation

Source Name: Stormwater Pond 1

  • purpose: miscellaneous (various on-Site usage)
  • maximum rate per minute (litres): 2,400
  • maximum number of hours of taking per day: 10
  • maximum volume per day (litres): 62,500
  • maximum number of days of taking per year: 240
  • earliest calendar date of taking (mm/dd): 04/01
  • latest calendar date of taking (mm/dd): 12/01
  • period of taking: 10 years

Source Name: Stormwater Pond 2

  • purpose: miscellaneous (various on-Site usage)
  • maximum rate per minute (litres): 2,400
  • maximum number of hours of taking per day: 10
  • maximum volume per day (litres): 105,000
  • maximum number of days of taking per year: 240
  • earliest calendar date of taking (mm/dd): 04/01
  • latest calendar date of taking (mm/dd): 12/01
  • period of taking: 10 years

Source Name: CD (excavation)

  • purpose: construction dewatering
  • maximum rate per minute (litres): 2,400
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 3,456,000
  • maximum number of days of taking per year: 365
  • earliest calendar date of taking (mm/dd): 01/01
  • latest calendar date of taking (mm/dd): 12/31
  • period of taking: 10 years

Source Name: SDL (pumping station)

  • purpose: construction dewatering
  • maximum rate per minute (litres): 900
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 1,296,000
  • maximum number of days of taking per year: 365
  • earliest calendar date of taking (mm/dd): 01/01
  • latest calendar date of taking (mm/dd): 12/31
  • period of taking: 10 years

Source Name: Purge Well System (wells PW1-PW10, PW20, PW26, PW27, PW30)

  • purpose: groundwater remediation
  • maximum rate per minute (litres): 1,421
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 2,045,700
  • maximum number of days of taking per year: 365
  • earliest calendar date of taking (mm/dd): 01/01
  • latest calendar date of taking (mm/dd): 12/31
  • period of taking: 10 years

Source Name: Pond (Dust)

  • purpose: miscellaneous (various on-site usage)
  • maximum rate per minute (litres): 42
  • maximum number of hours of taking per day: 10
  • maximum volume per day (litres): 25,000
  • maximum number of days of taking per year: 150
  • earliest calendar date of taking (mm/dd): 01/01
  • latest calendar date of taking (mm/dd): 12/31
  • period of taking: 10 years

Source Name: Pond (Poplar)

  • purpose: miscellaneous (various on-site usage)
  • maximum rate per minute (litres): 583
  • maximum number of hours of taking per day: 10
  • maximum volume per day (litres): 350,000
  • maximum number of days of taking per year: 200
  • earliest calendar date of taking (mm/dd): 01/01
  • latest calendar date of taking (mm/dd): 12/31
  • period of taking: 10 years

Source Name: Pond (Other)

  • purpose: miscellaneous (various on-site usage)
  • maximum rate per minute (litres): 52
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 75,000
  • maximum number of days of taking per year: 365
  • earliest calendar date of taking (mm/dd): 01/01
  • latest calendar date of taking (mm/dd): 12/31
  • period of taking: 10 years

There are 3 categories of a Permit to Take Water:

  • Category 1: water takings are anticipated to have a lower risk of causing an unacceptable environmental impact/interference
  • Category 2: water takings are anticipated to having a higher potential of causing unacceptable environmental impact or interference
  • Category 3: water takings are anticipated to have the highest potential of causing unacceptable environmental impactor interference

    The proposed water taking qualifies as a Category 1 permit.

    Documents justificatifs

    Consulter les documents en personne

    Certains documents justificatifs peuvent ne pas être accessibles en ligne. Si tel est le cas, vous pouvez demander à consulter les documents en personne.

    Veuillez communiquer avec le bureau mentionné ci-dessous pour savoir si les documents sont accessibles.

    Client Services and Permissions Branch
    Address

    135 St Clair Ave West
    1st Floor
    Toronto, ON
    M4V 1P5
    Canada

    Office phone number

    Commentaire

    La consultation est maintenant terminée.

    La période de consultation a eu lieu du 10 mars 2025
    au 9 avril 2025

    Communiquer avec nous

    Contact

    S'inscrire pour obtenir des avis

    Nous vous enverrons des avis par courriel accompagnés de toute mise à jour liée à cette consultation. Vous pouvez modifier vos préférences relatives à l'avis en tout temps en allant à votre page de profil où se trouvent vos paramètres.

    Suivre cet avis