Greenwich Windfarm GP Inc. - Environmental Compliance Approval (air)

Instrument type: Environmental Compliance Approval (air)

ERO number
026-0734
Ministry reference number
1913-DUQNLW
Notice type
Instrument
Act
Environmental Protection Act, R.S.O. 1990
Posted by
Ministry of the Environment, Conservation and Parks
Notice stage
Decision
Decision posted
Comment period
July 16, 2026 - August 30, 2026 (45 days) Closed
Last updated

This consultation was open from:
July 16, 2026
to August 30, 2026

Decision summary

Approval has been granted to amend the Environmental Compliance Approval (noise) No. 2070-7WJKDH for Greenwich Windfarm GP Inc. for the wind farm operation in the Township of Dorion, Ontario.

Location details

Site address

870 Greenwich Lake Road
Dorion, ON
Canada

Site location map

The location pin reflects the approximate area where environmental activity is taking place.

View this location on a map opens link in a new window

Proponent(s)

Greenwich Windfarm GP Inc.
870 Greenwich Lake Road
Dorion, ON
P0T 1K0
Canada

Decision details

Approval has been granted to amend the Environmental Compliance Approval (noise) No. 2070-7WJKDH for Greenwich Windfarm GP Inc. for the wind farm operation in the Township of Dorion, Ontario.

The Project currently consists of 43 as-built wind turbine generators (WTGs) and a transformer substation, equipped with 2 transformers.

This application is to reflect the as-built transformer substation locations.

Comments received

Through the registry

1

By email

1

By mail

0
View comments submitted through the registry

Effects of consultation

The ministry received one comment during the 45 day comment period from July 16 to August 30, 2026. The ministry also received another comment via email on October 9, 2026. The two comments were in reference to the lack of detail within the proposal notice to reflect the as-built transformer substation locations.

The Greenwich Wind Farm has an Environmental Compliance Approval (ECA) No. 2070-7WJKDH under the Environmental Protection Act, as the facility was approved before Ontario Regulation 359/09: Renewable Energy Approvals Under Part V.0.1 of the Act came into force.

The proposal is to update Schedule B in the amended ECA to include the locations of the as-built transformer substation. The Greenwich Wind Farm, consisting of 43 wind turbines and one transformer substation (equipped with two transformers) has been in commercial operation since 2011.

The only change as part of this amendment application is to reflect the final as-built layout of the transformer substation in the ECA.

An updated Acoustic Assessment Report (2026) was submitted as part of the application, and the assessment demonstrates that the noise levels from the facility will continue to comply with applicable MECP sound level limits at all identified points of reception. There are no noise-sensitive receptors located within 1,500 metres of the wind turbines or transformer substation.

Greenwich Windfarm GP Inc. must ensure that the facility is operating in compliance with their ECA.

Supporting materials

View materials in person

Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.

Get in touch with the office listed below to find out if materials are available.

Client Services and Permissions Branch
Address

40 St. Clair Avenue West
Floor 2
Toronto, ON
M4V 1M2
Canada

Office phone number
MECP Thunder Bay District
Address

435 James Street South
3rd Floor, Suite 331B
Thunder Bay, ON
P7E 6S7
Canada

Office phone number

How to Appeal

This instrument decision can be appealed. You have 15 days from October 23, 2026 to begin the appeal process.

Carefully review the information below to learn more about the appeal process.

How to appealClick to Expand Accordion

Start the process to appeal

If you’re an Ontario resident, you can start the process to appeal this instrument decision.

First, you’ll need to seek leave (i.e. get permission) from the relevant appellate body to appeal the decision.

If the appellate body grants leave, the appeal itself will follow.

Seek leave to appeal

To seek leave to appeal, you need to do these three things:

  1. prepare your application
  2. provide notice to the minister
  3. mail your application to three parties

1. Prepare your application

You’ll need to prepare an application. You may wish to include the following things in your application:

  1. A document that includes:
    • your name, phone number, fax number (if any), and/or email address
    • the ERO number and ministry reference number (located on this page)
    • a statement about whether you are a resident in Ontario
    • your interest in the decision, and any facts you want taken into account in deciding whether you have an interest in the decision
    • the parts of the instrument that you’re challenging
    • whether the decision could result in significant harm to the environment
    • the reason(s) why you believe that no reasonable person – having regard to the relevant law and to any government policies developed to guide decisions of that kind – could have made the decision
    • the grounds (facts) you’ll be using to appeal
    • the outcome you’d like to see
  2. A copy of the instrument (approval, permit, order) that you you are seeking leave to appeal. You’ll find this in the decision notice on the Environmental Registry
  3. Copies of all supporting documents, facts and evidence that you’ll be using to appeal
What is considered

The appeal body will consider the following two questions in deciding whether to grant you leave to appeal:

  1. is there is good reason to believe that no reasonable person, with respect to the relevant law and to any government policies developed to guide decisions of that kind, could have made the decision?
  2. could the decision you wish to appeal result in significant harm to the environment?

2. Provide your notice

You’ll need to provide notice to the Minister of the Environment, Conservation and Parks that you’re seeking leave to appeal.

In your notice, please include a brief description of the:

  • decision that you wish to appeal
  • grounds for granting leave to appeal

You can provide notice by email at minister.mecp@ontario.ca or by mail at:

College Park 5th Floor, 777 Bay St.
Toronto, ON
M7A 2J3

3. Mail your application

You’ll need to mail your application that you prepared in step #1 to each of these three parties:

  • appellate body
  • issuing authority (the ministry official who issued the instrument)
  • proponent (the company or individual to whom the instrument was issued)

Issuing authority
Neryed Ragbar
Manager (A) Priority Project Approvals

Environmental Permissions Branch
135 St Clair Avenue West
Floor 3
Toronto, ON
M4V 1P5
Canada

437-776-8348

Proponent(s)

Greenwich Windfarm GP Inc.
870 Greenwich Lake Road
Dorion, ON
P0T 1K0
Canada


Appellate body

Registrar, Ontario Land Tribunal
655 Bay Street, Suite 1500
Toronto, Ontario
M5G 1E5
(416) 212-6349
(866) 448-2248
OLT.Registrar@ontario.ca

About the Ontario Land Tribunal


Include the following:

ERO number
026-0734
Ministry reference number
1913-DUQNLW

This is not legal advice. Please refer to the Environmental Bill of Rights for exact legal requirements. Consult a lawyer if you need help with the appeal process.

Connect with us

Contact

Share

Email

Facebook

X

Sign up for notifications

We will send you email notifications with any updates related to this consultation. You can change your notification preferences anytime by visiting settings in your profile page.

Follow this notice

Original proposal

ERO number
026-0734
Ministry reference number
1913-DUQNLW
Notice type
Instrument
Act
Environmental Protection Act, R.S.O. 1990
Posted by
Ministry of the Environment, Conservation and Parks
Proposal posted

Comment period

July 16, 2026 - August 30, 2026 (45 days)

Proposal details

This proposal is to amend the Environmental Compliance Approval (noise) No. 2070-7WJKDH for Greenwich Windfarm GP Inc. for the wind farm operation in the Township of Dorion, Ontario.

The Project currently consists of 43 as-built wind turbine generators (WTGs) and a transformer substation, equipped with 2 transformers.

This application is to reflect the as-built substation transformer locations.

Supporting materials

View materials in person

Some supporting materials may not be available online. If this is the case, you can request to view the materials in person.

Get in touch with the office listed below to find out if materials are available.

Client Services and Permissions Branch
Address

40 St. Clair Avenue West
Floor 2
Toronto, ON
M4V 1M2
Canada

Office phone number

Comment

Commenting is now closed.