This decision is for a new Permit to Take Water for Dundas and Pacific Ltd. for construction dewatering purposes. Water will be taken from one well related to construction activities, located in the City of Toronto, Ontario.
A new Permit to Take Water No. 5127-BP4L3J was issued to Steed and Evans Limited. Water will be taken for concrete production and aggregate washing purposes.
Instrument type:
Changes to the site plan for a pit or quarry
ERO number
019-4768
Notice type
Instrument
Notice stage
Decision
Decision posted
Proposal posted
Comment period
December 14, 2021 - February 14, 2022 (62 days) Closed
Last updated
Approval was granted for a site plan amendment to allow Aaroc Aggregates Ltd. to remove aggregate from below the water table in a pit located in the township of Zorra.
A Certificate of Property Use was issued to the Regional Municipality of Waterloo for the property located at 188 Water Street South, in the City of Cambridge, on June 7, 2023.
February 7, 2020 - March 23, 2020 (45 days) Closed
Last updated
Approval has been granted for a new Environmental Compliance Approval for sewage works to service a residence located at 260 Ishkibbible Beach Road, in the Town of Shuniah.
Instrument type:
Changes to the site plan for a pit or quarry
ERO number
019-8065
Notice type
Instrument
Notice stage
Decision
Decision posted
Proposal posted
Comment period
December 21, 2023 - January 21, 2024 (31 days) Closed
Last updated
Approval was granted for a site plan amendment to allow Lafarge Canada Inc., in the Township of Zorra to operate the mobile processing plans in the Central Block of the site 24 hours per day, 7days per week. The approval authorizes several revisions to the Operational Site Plan to reflect the updated technical recommendations for noise.
Instrument type:
Approval for a consent (subject to conditions) in an area where there is no official plan in place
ERO number
019-3635
Notice type
Instrument
Notice stage
Decision
Decision posted
Proposal posted
Comment period
May 7, 2021 - June 6, 2021 (30 days) Closed
Last updated
Pursuant to Section 53 of the Planning Act, provisional consent was granted on July 23, 2021 in respect of Application 54-C-210389 for the creation of one new seasonal residential/recreational lot on lands in Tudhope unincorporated township, District of Timiskaming. The last day this decision can be appealed is August 12, 2021.
Instrument type:
Approval for a consent (subject to conditions) in an area where there is no official plan in place
ERO number
019-6578
Notice type
Instrument
Notice stage
Decision
Decision posted
Proposal posted
Comment period
January 30, 2023 - March 1, 2023 (30 days) Closed
Last updated
Application for Consent, 60-C-213247 to re-establish an agricultural parcel was granted provisional approval on March 7, 2023. The last day to appeal this decision is March 27, 2023.
Instrument type:
Changes to the conditions of a licence to operate a pit or quarry
ERO number
012-9848
Notice type
Instrument
Notice stage
Decision
Decision posted
Proposal posted
Comment period
February 14, 2017 - March 19, 2017 (33 days) Closed
Last updated
Approval was granted for a licence amendment to allow Carmeuse Lime (Canada) Limited to amalgamate licence No. 2136 with licence No. 2129 and No. 2130 under the reference number of ARA licence No. 2129. Approval was also granted to vary the tonnage condition for the amalgamated license No. 2129.
January 24, 2020 - February 23, 2020 (30 days) Closed
Last updated
We have issued a new Permit to Take Water No. 7271-BP5MWV on April 29, 2020 which cancels and replaces Permit To Take Water No. 7300-BAQNTK for The Oshawa Golf Club for golf course irrigation purposes in Oshawa, ON. Water will be taken from one (1) watercourse. The new Permit to Take Water has an expiry date of August 30, 2020.
We amended the Renewable Energy Approval for the Cochrane Solar Project to construct an access road between the Empire and Martin's Meadows areas of the facility; and to construct a storage building on the Martin's Meadows portion of the facility.
October 6, 2020 - November 20, 2020 (45 days) Closed
Last updated
The proposed amendments to the Mining Act allow the Minister in special circumstances to provide blanket exclusions of time or extensions of time for assessment work and allow for the Minister to annul the forfeiture of a boundary claim.
Instrument type:
Changes to the site plan for a pit or quarry
ERO number
019-6471
Notice type
Instrument
Notice stage
Decision
Decision posted
Proposal posted
Comment period
December 22, 2022 - January 23, 2023 (32 days) Closed
Last updated
Approval was granted for a site plan amendment to allow Roc Terra Soil Management Inc. to amend the current site plan to restore site to grade to allow for future agricultural uses, for a pit located in York Region.
Instrument type:
Approval for a consent (subject to conditions) in an area where there is no official plan in place
ERO number
019-7223
Notice type
Instrument
Notice stage
Decision
Decision posted
Proposal posted
Comment period
July 5, 2023 - August 4, 2023 (30 days) Closed
Last updated
Pursuant to Section 53 of the Planning Act, provisional consent was granted on October 3, 2023 in respect of Application 60-C-235426 for a lot addition for resource-based recreational use on lands described as PIN 42180-2576, in the community of Minaki, District of Kenora. The last day this decision can be appealed is October 23, 2023.