Update Announcement
This proposal notice is being updated to advise the public that the permit application is still under review and the Ministry is considering concerns raised by an Aboriginal community which warrant additional time to adequately consider. The original proposal date and comment period have not been changed.
Cette consultation a eu lieu :
du 27 octobre 2023
au 26 novembre 2023
Résumé de la proposition
The Ministry is proposing to issue a permit to Jon North (“the proponent”) to undertake early exploration activities.
Détails de l'emplacement
Détails de l'emplacement du site
The early exploration activities are located approximately 115 kilometres Northwest of Nipigon, Ontario, in English Bay Areas, District of Thunder Bay, Northwest Region.
Claim numbers instructions: To view individual claims on a map please use the Mining Lands Administration System. Click on “I want to…” and select “Find a claim” to search by claim numbers or “Find a township” to search by township.
Claim numbers: 840479, 840480, 840481, 840482, 840483, 840484, 840485, 840486, 840487, 840488, 840489, 840490, 840491, 840492, 840493, 840494, 840495, 840496, 840497, 840498, 840499, 840500, 840501, 840502, 840503, 840504, 840505, 840506, 840507, 840508, 840509, 840510, 840511, 840512, 840513, 840514, 840515, 840516, 840517, 840518, 842487, 842488, 842489, 842490, 842491
Carte de l'emplacement du site
L'épingle de localisation correspond à la zone approximative où a lieu l’activité environnementale.
Afficher cet emplacement sur une carte opens link in a new windowPromoteur(s)
Jon North
402 Reynolds Street
Oakville,
ON
L6J 3M4
Canada
Détails de la proposition
The proponent has submitted an application to the ministry for an exploration permit as required under the Mining Act for prescribed early exploration activities.
The activities that this permit would allow the proponent to carry out are as follows:
Permit activities
- mechanized stripping (greater than 100 square metres in a 200 metres radius)
- pitting and trenching of bedrock (greater than 3 cubic metres in a 200-metre radius)
The potential disturbance from the activities are described as:
Mechanized Surface Stripping: uses heavy equipment to remove vegetation and soil (overburden) from bedrock. The potential environmental disturbance includes (but are not limited to): use of heavy equipment such as bulldozers, backhoes, excavators or forest harvest equipment, to remove soil from the bedrock, washing the bedrock by pumping water from nearby lakes, rivers or streams, and creation of access trails.
Pitting and Trenching: are conducted to gain a greater visual understanding of the rock. The potential environmental disturbance includes (but is not limited to): the removal of surface soil, exposed rock as well as excavation or blasting of rock leaving shallow holes or trenches that vary in depth and length from the use of heavy equipment.
Proponents are required to follow provincial standards for early exploration to minimize the impacts to public health, safety and the environment from early exploration activities described above. You can find the standards in the Activities Information Sheets or on the Ministry website under Mining Act Policies, Standards and Directives (see links in “Related links” section).
This notice is provided to receive comments that can be considered in the decision-making process prior to the issuance of an exploration permit.
An Exploration Permit does not relieve the proponent from compliance with any other requirements that are set out under the Mining Act or any other Act. All activities included in the Exploration Permit proposal must be carried out in compliance with Ontario Regulation 308/12 and the Provincial Standards for Early Exploration. The Exploration Permit duration will be up to 3 years with the possibility of renewal.
Documents justificatifs
Consulter les documents en personne
Certains documents justificatifs peuvent ne pas être accessibles en ligne. Si tel est le cas, vous pouvez demander à consulter les documents en personne.
Veuillez communiquer avec le bureau mentionné ci-dessous pour savoir si les documents sont accessibles.
435 James Street South
Suite B002
Thunder Bay,
ON
P7E 6E3
Canada
Communiquer avec nous
Contact
Erin Kahkonen
435 James Street South
Suite B002
Thunder Bay,
ON
P7E 6E3
Canada
Commentaire
La consultation est maintenant terminée.
La période de consultation a eu lieu du 27 octobre 2023
au 26 novembre 2023