Cette consultation a eu lieu :
du 10 juillet 2025
au 9 août 2025
Résumé de la proposition
This proposal is for a renewal to Permit to Take Water No. P-300-3155282536 for Amrize Canada Inc. for Brockville Quarry. Water will be taken from the quarry sump for dewatering, aggregate washing, dust supression, and construction purposes in Brockville, Ontario.
Détails de l'emplacement
Adresse du site
1864 Highway 2
Brockville,
ON
Canada
Carte de l'emplacement du site
L'épingle de localisation correspond à la zone approximative où a lieu l’activité environnementale.
Afficher cet emplacement sur une carte opens link in a new windowPromoteur(s)
Amrize Canada Inc.
6509 Airport Road
Mississauga,
ON
L4V1S7
Canada
Détails de la proposition
This proposal is for a renewal to Permit to Take Water No. P-300-3155282536 for Amrize Canada Inc. for Brockville Quarry. Water will be taken from the quarry sump for dewatering, aggregate washing, dust supression, and construction purposes in Brockville, Ontario. Details of the water taking are as follows:
Permit type – renewal
Source name: Quarry Sump
- purpose: quarry dewatering
- maximum rate per minute (litres): 16,366
- maximum number of hours of taking per day: 24
- maximum volume per day (litres): 23,548,280
- maximum number of days of taking per year: 120
- earliest calendar date of taking (mm/dd): 01/01
- latest calendar date of taking (mm/dd): 12/31
- period of taking: 10 years
Source name: Quarry Sump
- purpose: quarry dewatering
- maximum rate per minute (litres): 10,910
- maximum number of hours of taking per day: 24
- maximum volume per day (litres): 15,710,400
- maximum number of days of taking per year: 245
- earliest calendar date of taking (mm/dd): 01/01
- latest calendar date of taking (mm/dd): 12/31
- period of taking: 10 years
Source name: Quarry Sump
- purpose: aggregate washing
- maximum rate per minute (litres): 16,366
- maximum number of hours of taking per day: 24
- maximum volume per day (litres): 23,548,280
- maximum number of days of taking per year: 306
- earliest calendar date of taking (mm/dd): 03/01
- latest calendar date of taking (mm/dd): 12/31
- period of taking: 10 years
Source name: Quarry Sump
- purpose: construction
- maximum rate per minute (litres): 10,910
- maximum number of hours of taking per day: 12
- maximum volume per day (litres): 2,000,000
- maximum number of days of taking per year: 306
- earliest calendar date of taking (mm/dd): 03/01
- latest calendar date of taking (mm/dd): 12/31
- period of taking: 10 years
Source name: Quarry Sump
- purpose: construction
- maximum rate per minute (litres): 10,910
- maximum number of hours of taking per day: 12
- maximum volume per day (litres): 2,000,000
- maximum number of days of taking per year: 306
- earliest calendar date of taking (mm/dd): 03/01
- latest calendar date of taking (mm/dd): 12/31
- period of taking: 10 years
There are 3 categories of a Permit to Take Water:
- Category 1: water takings are anticipated to have a lower risk of causing an unacceptable environmental impact/interference
- Category 2: water takings are anticipated to having a higher potential of causing unacceptable environmental impact or interference
- Category 3: water takings are anticipated to have the highest potential of causing unacceptable environmental impactor interference
The proposed water taking qualifies as a Category 3 permit.
Documents justificatifs
Consulter les documents en personne
Certains documents justificatifs peuvent ne pas être accessibles en ligne. Si tel est le cas, vous pouvez demander à consulter les documents en personne.
Veuillez communiquer avec le bureau mentionné ci-dessous pour savoir si les documents sont accessibles.
135 St Clair Ave West
1st Floor
Toronto,
ON
M4V 1P5
Canada
Communiquer avec nous
Contact
Client Services and Permissions Branch
135 St Clair Ave West
1st Floor
Toronto,
ON
M4V 1P5
Canada
Commentaire
La consultation est maintenant terminée.
La période de consultation a eu lieu du 10 juillet 2025
au 9 août 2025