Cette consultation a eu lieu :
du 23 mai 2019
au 7 juillet 2019
Résumé de la décision
We issued an Environmental Compliance Approval with Limited Operational Flexibility (Air) No. 0128-BCZRAH replacing all the current Environmental Compliance Approvals for air emissions at this facility including the addition of new and historically unapproved sources for all air emissions from Global Plas Inc.
Détails de l'emplacement
Adresse du site
300 Spinnaker Way
Concord,
ON
L4K 4N4
Canada
Carte de l'emplacement du site
L'épingle de localisation correspond à la zone approximative où a lieu l’activité environnementale.
Afficher cet emplacement sur une carte opens link in a new windowPromoteur(s)
Global Plas Inc.
300 Spinnaker Way
Vaughan,
ON
L4K 4W1
Canada
Détails de la décision
On August 22, 2019 we issued an Environmental Compliance Approval with Limited Operational Flexibility (Air) No. 0128-BCZRAH replacing all the current Environmental Compliance Approvals for air emissions at this facility. The approval includes the addition of new and historically unapproved sources for all air emissions from Global Plas Inc., an automotive parts manufacturing facility located at 300 Spinnaker Way, Concord, Ontario.
The approval includes emission from all processes at the facility, including:
- plastic injection moulding
- grinding
- automated adhesive application
- assembly
- packaging
- shipping
Emissions to the air from this facility include:
- suspended particulate matter
- benzaldehyde
- nitrogen oxide
- heavy hydrocarbon
- acrolein
- ketones
The Environmental Compliance Approval with Limited Operational Flexibility (Air) permits modifications to the facility subject to limits on operational flexibility that include a production limit for the facility specified on the Environmental Compliance Approval with Limited Operational Flexibility (Air).
The limited operational flexibility conditions have an expiry date.
The company is required to make an application for amendment to renew these conditions.
Documents justificatifs
Consulter les documents en personne
Certains documents justificatifs peuvent ne pas être accessibles en ligne. Si tel est le cas, vous pouvez demander à consulter les documents en personne.
Veuillez communiquer avec le bureau mentionné ci-dessous pour savoir si les documents sont accessibles.
135 St. Clair Avenue West
Floor 1
Toronto,
ON
M4V 1P5
Canada
230 Westney Road South
Floor 5
Ajax,
ON
L1S 7J5
Canada
How to Appeal
Cet avis de décision peut être porté en appel. Vous avez jusqu’à 15 jours à partir du 9 septembre 2019 pour entamer le processus d’appel.
Veuillez lire les renseignements suivants attentivement pour en savoir plus sur le processus d’appel.
Comment interjeter appelClick to Expand Accordion
For instrument decisions published on or after June 1, 2021, please refer to the updated instructions for information on how to appeal a decision.
Appeal process for decisions published before June 1, 2021
If you’re an Ontario resident, you can start the process to appeal this instrument decision.
First, you’ll need to seek leave (i.e. get permission) from the relevant appellate body to appeal the decision.
If the appellate body grants leave, the appeal itself will follow.
Seek leave to appeal
To seek leave to appeal, you need to do these three things:
- prepare your application
- provide notice to the minister
- mail your application to three parties
1. Prepare your application
You’ll need to prepare an application. You may wish to include the following things in your application:
- A document that includes:
- your name, phone number, fax number (if any), and/or email address
- the ERO number and ministry reference number (located on this page)
- a statement about whether you are a resident in Ontario
- your interest in the decision, and any facts you want taken into account in deciding whether you have an interest in the decision
- the parts of the instrument that you’re challenging
- whether the decision could result in significant harm to the environment
- the reason(s) why you believe that no reasonable person – having regard to the relevant law and to any government policies developed to guide decisions of that kind – could have made the decision
- the grounds (facts) you’ll be using to appeal
- the outcome you’d like to see
- A copy of the instrument (approval, permit, order) that you you are seeking leave to appeal. You’ll find this in the decision notice on the Environmental Registry
- Copies of all supporting documents, facts and evidence that you’ll be using to appeal
What is considered
The appeal body will consider the following two questions in deciding whether to grant you leave to appeal:
- is there is good reason to believe that no reasonable person, with respect to the relevant law and to any government policies developed to guide decisions of that kind, could have made the decision?
- could the decision you wish to appeal result in significant harm to the environment?
2. Provide your notice
You’ll need to provide notice to the Minister of the Environment, Conservation and Parks that you’re seeking leave to appeal.
In your notice, please include a brief description of the:
- decision that you wish to appeal
- grounds for granting leave to appeal
You can provide notice by email at minister.mecp@ontario.ca or by mail at:
College Park 5th Floor, 777 Bay St.
Toronto, ON
M7A 2J3
3. Mail your application
You’ll need to mail your application that you prepared in step #1 to each of these three parties:
- appellate body
- issuing authority (the ministry official who issued the instrument)
- proponent (the company or individual to whom the instrument was issued)
Global Plas Inc.
300 Spinnaker Way
Vaughan,
ON
L4K 4W1
Canada
Environmental Review Tribunal
Attention: The Secretary
655 Bay Street
Floor 15
Toronto, Ontario
M5G 1E5
(416) 212-6349
(866) 448-2248
OLT.Registrar@ontario.ca
Inclure les éléments suivants:
Il ne s'agit pas d'un avis juridique. Veuillez vous reporter à la Charte des droits environnementaux de 1993 pour connaître les exigences exactes prévues par la loi. Consultez un avocat si vous avez besoin d'aide avec le processus d'appel.
Communiquer avec nous
Contact
Application Assessment Officer
Proposition initiale
Détails de la proposition
Description of instrument
This proposal is for an Environmental Compliance Approval with Limited Operational Flexibility (Air) which replaces all the current Environmental Compliance Approvals for Air at this facility and includes the addition of new or historically unapproved sources for all emissions from Global Plas Inc., an automotive parts manufacturing facility located at 300 Spinnaker Way, Concord, Ontario.
The proposal includes emission from all processes at the facility, including:
- plastic injection moulding
- grinding
- automated adhesive application
- assembly
- packaging
- shipping
Emissions to the air from this facility include:
- suspended particulate matter
- benzaldehyde
- nitrogen oxide
- heavy hydrocarbon
- acrolein
- ketones
The Environmental Compliance Approval with Limited Operational Flexibility (Air), when issued permits modifications to the facility subject to limits on operational flexibility that include a production limit for the facility to be specified on the Environmental Compliance Approval with Limited Operational Flexibility (Air). The limited operational flexibility conditions have an expiry date. The company will be required to make an application for amendment at that time to renew these conditions. Andrea Solis
Documents justificatifs
Consulter les documents en personne
Certains documents justificatifs peuvent ne pas être accessibles en ligne. Si tel est le cas, vous pouvez demander à consulter les documents en personne.
Veuillez communiquer avec le bureau mentionné ci-dessous pour savoir si les documents sont accessibles.
135 St. Clair Avenue West
Floor 1
Toronto,
ON
M4V 1P5
Canada
230 Westney Road South
Floor 5
Ajax,
ON
L1S 7J5
Canada
Commentaire
La consultation est maintenant terminée.
Cette consultation a eu lieu 23 mai 2019
au 7 juillet 2019
Commentaires reçus
Par l'entremise du registre
0Par courriel
0Par la poste
0