Le présent avis est fourni à titre d’information seulement. Il n’existe aucune obligation de mener une consultation sur le Registre environnemental de l’Ontario à propos de cette initiative. Pour en savoir davantage sur le processus de consultation et les types d’avis publiés sur le registre.
Pourquoi une consultation n’est pas nécessaire
On April 1, 2020, the Ontario Government made a temporary regulation to respond to the COVID-19 outbreak. Ontario Regulation 115/20 exempted all proposals for policies, acts, regulations and instruments from posting requirements under the EBR.
Ontario Regulation 115/20 was revoked on June 15, 2020, however, we are posting this decision as a bulletin because the proposal was posted on April 7, 2020 while Ontario Regulation 115/20 was in effect.
Although consultation was not required, the ministry did consult with the public on this proposal by posting ERO# 019-1606 for public comment from April 7, 2020 to May 22, 2020. To ensure transparency, the ministry is providing details of its decision and the effects of consultation on decision-making in this notice.
Détails
Proponent
Peterson Spring of Canada Limited
Mail Address: 208 Wigle Avenue
Kingsville, Ontario
N9Y 2J9
Site Location
208 Wigle Avenue
Kingsville, Ontario
N9Y 2J9
Instrument decision
We issued an amended Environmental Compliance Approval (air) with Limited Operational Flexibility to Peterson Spring of Canada Limited, a manufacturer of spring components and replacement parts such as metal rings and other wire form products, located in the Town of Kingsville, Ontario.
The air emission sources from the manufacturing and associated processes include coiling, stress release ovens, grinding, shot peening, cold and hot setting, chamfering, burnishing, cap assembly, damper spring assembly, and painting.
The approval includes addition of a dust collector, updating the shot peeners, grinders, adding an electric oven, decommissioning the paint spinner and changing the product used in the paint spray booth.
Emissions to the air from this facility include hydrotreated naphthenic oil, resin, carbon black, diarylide yellow aaot, diarylide yellow hr, and products of combustion such as nitrogen oxides.
The Environmental Compliance Approval with Limited Operational Flexibility (air) permits modifications to the facility subject to limits on operational flexibility that include a production limit for the facility specified on the Environmental Compliance Approval with Limited Operational Flexibility (air). The limited operational flexibility conditions have an expiry date. The company is required to make an application for amendment at that time to renew these conditions.
Comments received
No comments were received.
Effects of consultation
Since we did not receive any comment during the commenting period, there is no impact of comment on the approval.
Third parties are not able to apply for leave to appeal in respect of proposals which were posted while Ontario Regulation 115/20 was in effect between April 1, 2020 and June 14, 2020. Ontario Regulation 115/20 exempted all proposals for instruments from posting requirements under the EBR. Leave to appeal may only be sought in respect of instruments that are required to be posted to the ERO.
Appeals information
Appeals are not allowed. This instrument type cannot be appealed.
Documents justificatifs
Consulter les documents en personne
Certains documents justificatifs peuvent ne pas être accessibles en ligne. Si tel est le cas, vous pouvez demander à consulter les documents en personne.
Veuillez communiquer avec le bureau mentionné ci-dessous pour savoir si les documents sont accessibles.
Communiquer avec nous
Contact
Client Services and Permissions Branch
135 St Clair Ave West
1st Floor
Toronto,
ON
M4V 1P5
Canada