Le présent avis porte sur une décision qui n’était pas assujettie au processus de consultation normal. Pour en savoir davantage sur le processus de consultation et les types d’avis publiés sur le registre.
Détails de l'emplacement
Adresse du site
789 King Avenue East
Newcastle,
ON
Canada
Carte de l'emplacement du site
L'épingle de localisation correspond à la zone approximative où a lieu l’activité environnementale.
Afficher cet emplacement sur une carte opens link in a new windowDétails de la proposition
10657433 Canada Ltd. (operating as Castle John’s Pub and Restaurant)
15 Purdue Avenue
Ajax,
ON
L1T 4L2
Canada
Pourquoi une consultation n’est pas nécessaire
The ministry has relied on section 29 of the Environmental Bill of Rights, 1993 (EBR), as it is the Director’s opinion that the delay in giving notice to the public of the proposal for the instrument, allowing for public participation, and in considering the response to the notice would have resulted in:
- danger to the health and safety of any person
- harm or serious risk of harm to the environment; or
- injury or damage or serious risk of injury or damage to any property
The ministry is posting this exception notice to give notice of its decision to rely on section 29 of the EBR.
Détails de l'exception
We issued a new Environmental Compliance Approval on December 11, 2020 for a 16,250 L/day septic system to service a restaurant and motel. The approval was for upgrades to the existing sewage works, which had failed and was contaminating water within a sump pump on site and was discharging into a nearby wetland. A temporary collection system was in place to collect the contaminated water, but this temporary system may not operate effectively during the winter months. It was the opinion of the Director that posting the proposed instrument for public comment would have resulted in danger to the health or safety of any person using this facility, harm or serious risk of harm to the environment, and injury or damage or serious risk of injury or damage to the property given the existing system had failed and the temporary system in place could not operate in winter conditions, as outlined below:
- a sump pump at the restaurant discharges via a pipe to a wetland south of the site. The sump pump was drawing in sewage from the failed existing system and discharging contaminated water into the wetland, which is adjacent to a neighbouring trailer park. This was causing ongoing odour complaints from the trailer park and also presented risk of exposure of public to raw sewage
- the contaminated discharge was recently re-directed to a large 18,000 litre (4,000 Imperial gallon) capacity concrete holding tank, which required regular pump out. As the holding tank was concrete and was placed on the ground outdoors, the ministry was concerned the tank and the pipes would freeze during the winter.
- given the potential for the temporary system to fail, the best engineering approach was to replace the failed system before there was a risk of a significant frost event. This would eliminate the potential release of raw sewage into the environment
Details of issued Environmental Compliance Approval
The ministry has issued a new Environmental Compliance Approval (sewage) for 10657433 Canada Ltd. for the replacement and upgrade of the failed subsurface disposal works, servicing a commercial facility at 789 King Avenue East, Newcastle, Municipality of Clarington, Ontario.
The commercial facility consists of a sports bar and an attached 8-unit motel with future plans for an additional 8 units.
The replacement sewage works up-grade is sized for a design capacity of daily sewage flow at 16,250 litres per day.
The upgraded system will comprise of an exterior grease trap, septic tank, pumping chamber and leaching bed.
Administrative error: original proposal notice
A proposal notice was posted on the Environmental Registry (ERO # 019-2755) on November 26, 2020 with a 45 day public review and comment period that would have ended on January 10, 2021.
The proposal notice was posted in error. The Director was – and continues to be – of the opinion that the delay involved in giving notice to the public, in allowing time for public response to the notice or in considering the response to the notice would result in danger to the health or safety of any person; harm or serious risk of harm to the environment; and injury or damage or serious risk of injury or damage to any property as detailed above.
Documents justificatifs
Consulter les documents en personne
Certains documents justificatifs peuvent ne pas être accessibles en ligne. Si tel est le cas, vous pouvez demander à consulter les documents en personne.
Veuillez communiquer avec le bureau mentionné ci-dessous pour savoir si les documents sont accessibles.
Communiquer avec nous
Personne-ressource
Client Services and Permissions Branch
135 St Clair Ave West
1st Floor
Toronto,
ON
M4V 1P5
Canada