Résumé de la décision
This decision is to refuse the amendment to Permit to Take Water No. 6834-BVBRSJ for Pure Gold Mining Inc. for industrial purposes. Water was requested to be taken from one pond to support underground mining operations at the Puregold Mine, located in Madsen, Ontario.
Détails de l'emplacement
Adresse du site
2 Mine Street
Madsen,
ON
Canada
Carte de l'emplacement du site
L'épingle de localisation correspond à la zone approximative où a lieu l’activité environnementale.
Afficher cet emplacement sur une carte opens link in a new windowPromoteur(s)
Pure Gold Mining Inc.
2 Mine Street, P.O. Box 304
Madsen,
ON
P0V 2C0
Canada
Détails de la décision
This decision is to refuse the amendment to Permit to Take Water No. 6834-BVBRSJ for Pure Gold Mining Inc. for industrial purposes. Water was requested to be taken from one pond to support underground mining operations at the Puregold Mine, located in Madsen, Ontario.
This refused amendment was to request an averaging condition to water taken from the pond over a monthly basis versus a daily basis. The application was refused as it was submitted with an incorrect category and therefore, does not have the necessary supporting documentation for us to process the application.
Details of the requested water taking are as follows:
Source name: process water pond
- purpose: industrial - underground mining
- maximum rate per minute (litres): 400
- maximum number of hours of taking a day: 24
- maximum volume per day (litres): 300,000
- maximum number of days taken per year: 365
- duration: January 1 to December 31 for 10 years
Documents justificatifs
Consulter les documents en personne
Certains documents justificatifs peuvent ne pas être accessibles en ligne. Si tel est le cas, vous pouvez demander à consulter les documents en personne.
Veuillez communiquer avec le bureau mentionné ci-dessous pour savoir si les documents sont accessibles.
435 James Street South
Floor 3, Suite 331
Thunder Bay,
ON
P7E 6S7
Canada
How to Appeal
Cet avis de décision peut être porté en appel. Vous avez jusqu’à 15 jours à partir du 1 juin 2022 pour entamer le processus d’appel.
Veuillez lire les renseignements suivants attentivement pour en savoir plus sur le processus d’appel.
Comment interjeter appelClick to Expand Accordion
For instrument decisions published on or after June 1, 2021, please refer to the updated instructions for information on how to appeal a decision.
Appeal process for decisions published before June 1, 2021
If you’re an Ontario resident, you can start the process to appeal this instrument decision.
First, you’ll need to seek leave (i.e. get permission) from the relevant appellate body to appeal the decision.
If the appellate body grants leave, the appeal itself will follow.
Seek leave to appeal
To seek leave to appeal, you need to do these three things:
- prepare your application
- provide notice to the minister
- mail your application to three parties
1. Prepare your application
You’ll need to prepare an application. You may wish to include the following things in your application:
- A document that includes:
- your name, phone number, fax number (if any), and/or email address
- the ERO number and ministry reference number (located on this page)
- a statement about whether you are a resident in Ontario
- your interest in the decision, and any facts you want taken into account in deciding whether you have an interest in the decision
- the parts of the instrument that you’re challenging
- whether the decision could result in significant harm to the environment
- the reason(s) why you believe that no reasonable person – having regard to the relevant law and to any government policies developed to guide decisions of that kind – could have made the decision
- the grounds (facts) you’ll be using to appeal
- the outcome you’d like to see
- A copy of the instrument (approval, permit, order) that you you are seeking leave to appeal. You’ll find this in the decision notice on the Environmental Registry
- Copies of all supporting documents, facts and evidence that you’ll be using to appeal
What is considered
The appeal body will consider the following two questions in deciding whether to grant you leave to appeal:
- is there is good reason to believe that no reasonable person, with respect to the relevant law and to any government policies developed to guide decisions of that kind, could have made the decision?
- could the decision you wish to appeal result in significant harm to the environment?
2. Provide your notice
You’ll need to provide notice to the Minister of the Environment, Conservation and Parks that you’re seeking leave to appeal.
In your notice, please include a brief description of the:
- decision that you wish to appeal
- grounds for granting leave to appeal
You can provide notice by email at minister.mecp@ontario.ca or by mail at:
College Park 5th Floor, 777 Bay St.
Toronto, ON
M7A 2J3
3. Mail your application
You’ll need to mail your application that you prepared in step #1 to each of these three parties:
- appellate body
- issuing authority (the ministry official who issued the instrument)
- proponent (the company or individual to whom the instrument was issued)
Pure Gold Mining Inc.
2 Mine Street, P.O. Box 304
Madsen,
ON
P0V 2C0
Canada
Environmental Review Tribunal
Attention: The Secretary
655 Bay Street
Floor 15
Toronto, Ontario
M5G 1E5
(416) 212-6349
(866) 448-2248
OLT.Registrar@ontario.ca
Inclure les éléments suivants:
Il ne s'agit pas d'un avis juridique. Veuillez vous reporter à la Charte des droits environnementaux de 1993 pour connaître les exigences exactes prévues par la loi. Consultez un avocat si vous avez besoin d'aide avec le processus d'appel.
Communiquer avec nous
Contact
Client Services and Permissions Branch
135 St Clair Ave West
1st Floor
Toronto,
ON
M4V 1P5
Canada
Proposition initiale
Détails de la proposition
This proposal is to amend Permit to Take Water No. 6834-BVBRSJ for Pure Gold Mining Inc. for industrial purposes. Water will be taken from one pond to support underground mining operations at the Puregold Mine, located in Madsen, Ontario.
This amendment is to request an averaging condition to water taken from the pond over a monthly basis versus a daily basis. Details of the water taking are as follows:
Source name: process water pond
- purpose: industrial - underground mining
- maximum rate per minute (litres): 400
- maximum number of hours of taking a day: 24
- maximum volume per day (litres): 300,000
- maximum number of days taken per year: 365
- duration: January 1 to December 31 for 10 years
Documents justificatifs
Consulter les documents en personne
Certains documents justificatifs peuvent ne pas être accessibles en ligne. Si tel est le cas, vous pouvez demander à consulter les documents en personne.
Veuillez communiquer avec le bureau mentionné ci-dessous pour savoir si les documents sont accessibles.
Commentaire
La consultation est maintenant terminée.
Cette consultation a eu lieu 29 mars 2022
au 28 avril 2022
Communiquer avec nous
Contact
Client Services and Permissions Branch
135 St Clair Ave West
1st Floor
Toronto,
ON
M4V 1P5
Canada