The Director of Exploration has made a decision on the exploration permit application PR-25-000117 to Silver Lake Ontario Inc. for early exploration activities.
The decision is to issue the mineral exploration permit.
The Director of Exploration has made a decision on the exploration permit application PR-25-000116 to Silver Lake Ontario Inc. for early exploration activities.
The decision is to issue the mineral exploration permit.
The Director of Exploration has made a decision on the exploration permit application PR-25-000122 to Fortune Nickel and Gold Inc. for early exploration activities.
The decision is to issue the mineral exploration permit.
The Director of Exploration has made a decision on the exploration permit application PR-25-000121 to Fortune Nickel and Gold Inc. for early exploration activities.
The decision is to issue the mineral exploration permit.
The Director has exercised her powers under subsection 20.7 (2) and 20.13 of the Environmental Protection Act to revoke Environmental Compliance Approval Number 6884-AGVMAN which was issued for the establishment of stormwater management works servicing the site.
We are moving forward with regulatory changes to make it easier for proponents to apply for a permit to take water when a previous permit has been cancelled, revoked, or expired within the past year in limited circumstances. These changes will give applicants more flexibility while maintaining oversight.
Amended Environmental Compliance Approval (ECA) is granted to CHR Canada Group Inc. for groundwater and stormwater management and discharge at the Milton North Quarry, located in the Town of Milton.
Approval is granted for a new Environmental Compliance Approval for industrial stormwater management works serving Skyview BESS Inc., located at Parts of Lots 1, 2, 3, Concession 8, in the Township of Edwardsburgh/Cardinal, Ontario.
The Director of Exploration has made a decision on the exploration permit application PR-25-00041 to 5051318 Ontario Corp., for early exploration activities.
The decision is to issue the mineral exploration permit.
The Director of Exploration has made a decision on the exploration permit application PR-25-000110 to Canada Nickel Company Inc. for early exploration activities.
The decision is to issue the mineral exploration permit.
The Director of Exploration has made a decision on the exploration permit application PR-25-000105 to Wabassi Resources for early exploration activities.&
The decision is to: issue the mineral exploration permit.
November 7, 2023 - December 22, 2023 (45 days) Closed
Last updated
The ministry has issued a new Environmental Compliance Approval for the establishment of subsurface sewage disposal works rated at 37,700 litres per day, to service a campground located at 108 Miller Lake Shore Road, in the Town of Northern Bruce Peninsula.
Amended Environmental Compliance Approval was issued with conditions. This amendment was to approve the removal of pond C sludge to decommission pond C.
November 8, 2024 - December 23, 2024 (45 days) Closed
Last updated
The ministry has issued a new Environmental Compliance Approval (sewage) to Hydro Ottawa Limited to construct new spill containment systems to service a proposed Municipal Hydro Transformer Substation located at 5134 Piperville Road, in the City of Ottawa, Ontario.
August 18, 2023 - October 2, 2023 (45 days) Closed
Last updated
Establishment of an industrial stormwater management Works to serve Great Lakes Port Management Inc. (GLPM), trucking/trailer site, located in the City of Thorold, for the collection, transmission, treatment and disposal of stormwater run-off from a total catchment area of approximately 5.0 hectares, to provide normal level water quality.
The ministry has issued a new Environmental Compliance Approval (sewage) to Toronto Hydro-Electric System Limited for the installation of an oil containment system as part of transformer replacement work serving electrical utility distribution stations, located at 62 Elmhurst Drive, in the City of Toronto, Ontario.
Instrument type:
Approval of an amendment to the Niagara Escarpment Plan
ERO number
019-5928
Notice type
Instrument
Notice stage
Decision
Decision posted
Proposal posted
Comment period
September 1, 2022 - October 31, 2022 (60 days) Closed
Last updated
A decision was made to approve an amendment to the Niagara Escarpment Plan to re-designate 30.5 ha of land from Escarpment Rural Area to Mineral Resource Extraction Area to facilitate an expansion to the existing Dufferin Milton quarry and to approve site specific policy amendments to support the expansion.
October 18, 2023 - December 2, 2023 (45 days) Closed
Last updated
We have approved a new Environmental Compliance Approval No. 2936-DHGLJZ for York1 Tiffin Recycling Ltd. for the construction and operation of a waste disposal site (processing) located within a 1.639 hectares total site area located at 529 Tiffin Street in the City of Barrie.