Freymond Lumber Limited - Environmental Compliance Approval (sewage)

La traduction française de cet avis n'est pas disponible. Nous nous excusons pour le dérangement.

Type d'acte: Environmental Compliance Approval (sewage)

Numéro du REO
019-6711
Numéro de référence du ministère
1000208996
Type d'avis
Instrument
Loi
Environmental Protection Act, R.S.O. 1990
Affiché par
Ministry of the Environment, Conservation and Parks
Étape de l'avis
Proposition Mis à jour
Proposition affichée
Période de consultation
Du 2 mars 2023 au 16 avril 2023 (45 jours) Fermé
Dernière mise à jour

Update Announcement

This proposal notice was updated on August 30, 2024 to advise the public that this file is still under active review. The original proposal date and comment period have not been altered

Cette consultation a eu lieu :

du 2 mars 2023
au 16 avril 2023

Résumé de la proposition

The proposal is for a new Environmental Compliance Approval for Freymond Lumber Limited for stormwater management works serving Phase 1 of the Freymond Quarry, located at 2287 Bay Lake Road in Bancroft, Ontario.

Détails de l'emplacement

Adresse du site

2287 Bay Lake Road
Bancroft, ON
Canada

Carte de l'emplacement du site

L'épingle de localisation correspond à la zone approximative où a lieu l’activité environnementale.

Afficher cet emplacement sur une carte opens link in a new window

Promoteur(s)

Freymond Lumber Limited
2287 Bay Lake Road
Bancroft, ON
K0L 1C0
Canada

Détails de la proposition

The proposal is for a new Environmental Compliance Approval for Freymond Lumber Limited for stormwater management works at the Freymond Quarry, located at 2287 Bay Lake Road in Bancroft, Ontario.

The stormwater management works comprise of a stormwater management dry pond, also referred to as an infiltration cell, that will contain and manage stormwater runoff from Phase 1 of the Freymond Quarry. The infiltration cell is proposed for the east corner of the site, in the designated area for the stormwater management pond.

While Phase 1 is being extracted, the proposed infiltration cell will provide quality, quantity, and erosion control protection by infiltrating all stormwater runoff from storm events up to and including the 100-year event.

The proposed infiltration cell is sized to fully infiltrate all runoff, with no outlet. The infiltration cell will have no direct discharge to a water body nor a water channel. Infiltration will occur from the bottom of the infiltration cell. The infiltration cell will be inspected regularly after storm events to ensure it is performing properly.

Documents justificatifs

Consulter les documents en personne

Certains documents justificatifs peuvent ne pas être accessibles en ligne. Si tel est le cas, vous pouvez demander à consulter les documents en personne.

Veuillez communiquer avec le bureau mentionné ci-dessous pour savoir si les documents sont accessibles.

Client Services and Permissions Branch
Address

135 St. Clair Avenue West
Floor 1
Toronto, ON
M4V 1P5
Canada

Office phone number

Commentaire

La consultation est maintenant terminée.

La période de consultation a eu lieu du 2 mars 2023