Résumé de la proposition
This proposal is for an amendment to Permit to Take Water No. 0776-D3PFY2 for Ontario Power Generation No.. Water will be taken from 11 wells for construction dewatering purposes, located in the Town of Bowmanville, Ontario. The proposed amendment includes the addition of five wells (sandpoints).
Détails de l'emplacement
Adresse du site
2nd Line Road at the Holt Road Extension
Bowmanville,
ON
Canada
Carte de l'emplacement du site
L'épingle de localisation correspond à la zone approximative où a lieu l’activité environnementale.
Afficher cet emplacement sur une carte opens link in a new windowPromoteur(s)
Ontario Power Generation Inc.
1908 Colonel Sam Drive
Oshawa,
ON
L1H 8W8
Canada
Détails de la proposition
This proposal is for an amendment to Permit to Take Water No. 0776-D3PFY2 for Ontario Power Generation Inc. Water will be taken from eleven 11 wells for construction dewatering purposes, located in the Town of Bowmanville, Ontario.
The proposed amendment includes the addition of five wells (sandpoints). Details of the water taking are as follows:
Permit type – amendment
Source Name: Underground Servicing Trench
- purpose: construction dewatering
- maximum rate per minute (litres): 140
- maximum number of hours of taking per day: 24
- maximum volume per day (litres): 202,000
- maximum number of days of taking per year: 364
- period of taking: January 1 to December 31 for three years
Source Name: Building Footing
- purpose: construction dewatering
- maximum rate per minute (litres): 36
- maximum number of hours of taking per day: 24
- maximum volume per day (litres): 52,000
- maximum number of days of taking per year: 364
- period of taking: January 1 to December 31 for three years
Source Name: SMR 1 Overburden Excavation
- purpose: construction dewatering
- maximum rate per minute (litres): 180
- maximum number of hours of taking per day: 24
- maximum volume per day (litres): 260,000
- maximum number of days of taking per year: 364
- period of taking: January 1 to December 31 for three years
Source Name: SMR 1 Shaft Excavation
- purpose: construction dewatering
- maximum rate per minute (litres): 250
- maximum number of hours of taking per day: 24
- maximum volume per day (litres): 360,000
- maximum number of days of taking per year: 364
- period of taking: January 1 to December 31 for three years
Source Name: CCW Outfall Shaft Excavation
- purpose: construction dewatering
- maximum rate per minute (litres): 375
- maximum number of hours of taking per day: 24
- maximum volume per day (litres): 540,000
- maximum number of days of taking per year: 364
- period of taking: January 1 to December 31 for three years
Source Name: Forebay/ CCW Intake Shaft Excavation
- purpose: construction dewatering
- maximum rate per minute (litres): 333
- maximum number of hours of taking per day: 24
- maximum volume per day (litres): 480,000
- maximum number of days of taking per year: 364
- period of taking: January 1 to December 31 for three years
Source Name: Cooling Water System Trench
- purpose: construction dewatering
- maximum rate per minute (litres): 280
- maximum number of hours of taking per day: 24
- maximum volume per day (litres): 404,000
- maximum number of days of taking per year: 364
- period of taking: January 1 to December 31 for three years
Source Name: SMR 2, 3 and 4 Shafts
- purpose: construction dewatering
- maximum rate per minute (litres): 309
- maximum number of hours of taking per day: 24
- maximum volume per day (litres): 446,000
- maximum number of days of taking per year: 364
- period of taking: January 1 to December 31 for three years
Source Name: Transmission Towers Caissons
- purpose: construction dewatering
- maximum rate per minute (litres): 66
- maximum number of hours of taking per day: 24
- maximum volume per day (litres): 96,000
- maximum number of days of taking per year: 364
- period of taking: January 1 to December 31 for three years
Source Name: Bridge Structure Caissons
- purpose: construction dewatering
- maximum rate per minute (litres): 250
- maximum number of hours of taking per day: 24
- maximum volume per day (litres): 360,000
- maximum number of days of taking per year: 364
- period of taking: January 1 to December 31 for three years
Source Name: Caissons for Powerhouse Structures
- purpose: construction dewatering
- maximum rate per minute (litres): 267
- maximum number of hours of taking per day: 24
- maximum volume per day (litres): 385,000
- maximum number of days of taking per year: 364
- period of taking: January 1 to December 31 for three years
There are 3 categories of a Permit to Take Water:
- Category 1: water takings are anticipated to have a lower risk of causing an unacceptable environmental impact/interference
- Category 2: water takings are anticipated to having a higher potential of causing unacceptable environmental impact or interference
- Category 3: water takings are anticipated to have the highest potential of causing unacceptable environmental impactor interference
The proposed water taking qualifies as a Category 3 permit.
Documents justificatifs
Consulter les documents en personne
Certains documents justificatifs peuvent ne pas être accessibles en ligne. Si tel est le cas, vous pouvez demander à consulter les documents en personne.
Veuillez communiquer avec le bureau mentionné ci-dessous pour savoir si les documents sont accessibles.
135 St. Clair Avenue West
Floor 1
Toronto,
ON
M4V 1P5
Canada
Communiquer avec nous
Contact
Client Services and Permissions Branch
135 St Clair Ave West
1st Floor
Toronto,
ON
M4V 1P5
Canada
Commentaire
Dites-nous ce que vous pensez de notre proposition.
Vous avez des questions? Contactez la personne-ressource indiquée ci-dessous. Veuillez indiquer le numéro du REO de l’avis dans votre courriel ou votre lettre à la personne-ressource.Lire nos politiques relatives aux commentaires et à la protection de la vie privée.
Soumettre en ligne
Soumettre par la poste
Contact
Client Services and Permissions Branch
135 St Clair Ave West
1st Floor
Toronto, ON
M4V 1P5
Canada