Ontario Power Generation Inc. - Permit to take water

La traduction française de cet avis n'est pas disponible. Nous nous excusons pour le dérangement.

Type d'acte: Permit to take water

Numéro du REO
025-0371
Numéro de référence du ministère
7322-DF7ND3
Type d'avis
Instrument
Loi
Ontario Water Resources Act, R.S.O. 1990
Affiché par
Ministry of the Environment, Conservation and Parks
Étape de l'avis
Proposition
Proposition affichée
Période de consultation
Du 9 avril 2025 au 9 mai 2025 (30 jours) Ouvert
Dernière mise à jour

Cette consultation se termine à 23 h 59 le :
9 mai 2025

Résumé de la proposition

This proposal is for an amendment to Permit to Take Water No. 0776-D3PFY2 for Ontario Power Generation No.. Water will be taken from 11 wells for construction dewatering purposes, located in the Town of Bowmanville, Ontario. The proposed amendment includes the addition of five wells (sandpoints).

Détails de l'emplacement

Adresse du site

2nd Line Road at the Holt Road Extension
Bowmanville, ON
Canada

Carte de l'emplacement du site

L'épingle de localisation correspond à la zone approximative où a lieu l’activité environnementale.

Afficher cet emplacement sur une carte opens link in a new window

Promoteur(s)

Ontario Power Generation Inc.
1908 Colonel Sam Drive
Oshawa, ON
L1H 8W8
Canada

Détails de la proposition

This proposal is for an amendment to Permit to Take Water No. 0776-D3PFY2 for Ontario Power Generation Inc. Water will be taken from eleven 11 wells for construction dewatering purposes, located in the Town of Bowmanville, Ontario.

The proposed amendment includes the addition of five wells (sandpoints). Details of the water taking are as follows:

Permit type – amendment

Source Name: Underground Servicing Trench

  • purpose: construction dewatering
  • maximum rate per minute (litres): 140
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 202,000
  • maximum number of days of taking per year: 364
  • period of taking: January 1 to December 31 for three years

Source Name: Building Footing

  • purpose: construction dewatering
  • maximum rate per minute (litres): 36
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 52,000
  • maximum number of days of taking per year: 364
  • period of taking: January 1 to December 31 for three years

Source Name: SMR 1 Overburden Excavation

  • purpose: construction dewatering
  • maximum rate per minute (litres): 180
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 260,000
  • maximum number of days of taking per year: 364
  • period of taking: January 1 to December 31 for three years

Source Name: SMR 1 Shaft Excavation

  • purpose: construction dewatering
  • maximum rate per minute (litres): 250
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 360,000
  • maximum number of days of taking per year: 364
  • period of taking: January 1 to December 31 for three years

Source Name: CCW Outfall Shaft Excavation

  • purpose: construction dewatering
  • maximum rate per minute (litres): 375
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 540,000
  • maximum number of days of taking per year: 364
  • period of taking: January 1 to December 31 for three years

Source Name: Forebay/ CCW Intake Shaft Excavation

  • purpose: construction dewatering
  • maximum rate per minute (litres): 333
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 480,000
  • maximum number of days of taking per year: 364
  • period of taking: January 1 to December 31 for three years

Source Name: Cooling Water System Trench

  • purpose: construction dewatering
  • maximum rate per minute (litres): 280
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 404,000
  • maximum number of days of taking per year: 364
  • period of taking: January 1 to December 31 for three years

Source Name: SMR 2, 3 and 4 Shafts

  • purpose: construction dewatering
  • maximum rate per minute (litres): 309
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 446,000
  • maximum number of days of taking per year: 364
  • period of taking: January 1 to December 31 for three years

Source Name: Transmission Towers Caissons

  • purpose: construction dewatering
  • maximum rate per minute (litres): 66
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 96,000
  • maximum number of days of taking per year: 364
  • period of taking: January 1 to December 31 for three years

Source Name: Bridge Structure Caissons

  • purpose: construction dewatering
  • maximum rate per minute (litres): 250
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 360,000
  • maximum number of days of taking per year: 364
  • period of taking: January 1 to December 31 for three years

Source Name: Caissons for Powerhouse Structures

  • purpose: construction dewatering
  • maximum rate per minute (litres): 267
  • maximum number of hours of taking per day: 24
  • maximum volume per day (litres): 385,000
  • maximum number of days of taking per year: 364
  • period of taking: January 1 to December 31 for three years

There are 3 categories of a Permit to Take Water:

  • Category 1: water takings are anticipated to have a lower risk of causing an unacceptable environmental impact/interference
  • Category 2: water takings are anticipated to having a higher potential of causing unacceptable environmental impact or interference
  • Category 3: water takings are anticipated to have the highest potential of causing unacceptable environmental impactor interference

The proposed water taking qualifies as a Category 3 permit.

Documents justificatifs

Consulter les documents en personne

Certains documents justificatifs peuvent ne pas être accessibles en ligne. Si tel est le cas, vous pouvez demander à consulter les documents en personne.

Veuillez communiquer avec le bureau mentionné ci-dessous pour savoir si les documents sont accessibles.

Client Services and Permissions Branch
Address

135 St. Clair Avenue West
Floor 1
Toronto, ON
M4V 1P5
Canada

Office phone number

Commentaire

Dites-nous ce que vous pensez de notre proposition.

Vous avez des questions? Contactez la personne-ressource indiquée ci-dessous. Veuillez indiquer le numéro du REO de l’avis dans votre courriel ou votre lettre à la personne-ressource.

Lire nos politiques relatives aux commentaires et à la protection de la vie privée.

Soumettre en ligne

Soumettre par la poste

Contact

Communiquer avec nous

Contact

S'inscrire pour obtenir des avis

Nous vous enverrons des avis par courriel accompagnés de toute mise à jour liée à cette consultation. Vous pouvez modifier vos préférences relatives à l'avis en tout temps en allant à votre page de profil où se trouvent vos paramètres.

Suivre cet avis