Résumé de la décision
The Director of Mine Rehabilitation has acknowledged receipt of the Closure Plan according to the provisions of the Mining Act. The Certified Closure Plan is now considered filed and the proponent must comply with the Closure Plan.
Détails de l'emplacement
Détails de l'emplacement du site
The Black Fox Mine site is located in Hislop township and approximately 10 kilometres east of the town of Matheson. Current access is via highway 101.
The Complex consists of one block of land comprising 34 parcels (30 mining patents and four leases for surface rights only), for a total of 1,301 ha. Some parcels and mining titles are subject to royalties. All parcels and mining titles are either freehold mining lands (mining patents), a mining lease, or a licence of occupation. The Land Tenure Summary is available under "Supporting Materials".
Carte de l'emplacement du site
L'épingle de localisation correspond à la zone approximative où a lieu l’activité environnementale.
Afficher cet emplacement sur une carte opens link in a new windowPromoteur(s)
10393444 Canada Incorporated
150 King Street West
Suite 2800, P.O. Box 24
Toronto,
ON
M5H 1J9
Canada
Détails de la décision
On 30/06/21 ENDM filed a certified amendment for the Black Fox Mine site, located in Hislop township and approximately 10 km east of the town of Matheson. The filed amendment updates the following aspects of the filed Closure Plan:
- environmental conditions at the site
- project description
- rehabilitation measures
- monitoring program
- expected site conditions after closure, and
- expected costs of reclamation
Effets de la consultation
No comment was received through the Environmental Registry of Ontario resulting in no impact on the decision to proceed or not with this amendment to closure plan.
Documents justificatifs
Consulter les documents en personne
Certains documents justificatifs peuvent ne pas être accessibles en ligne. Si tel est le cas, vous pouvez demander à consulter les documents en personne.
Veuillez communiquer avec le bureau mentionné ci-dessous pour savoir si les documents sont accessibles.
5520 Highway 101 E Highway
PO Box 3060
South Porcupine Ontario,
ON
P0N 1H0
Canada
How to Appeal
Les appels ne sont pas autorisés
Ce type d’acte ne peut être porté en appel. En savoir plus sur notre processus de consultation.
Communiquer avec nous
Contact
Andrew Persad
5520 Highway 101 East
PO Box 3060
South Porcupine,
ON
P0N 1H0
Canada
Proposition initiale
Détails de la proposition
McEwen Ontario has submitted a certified amendment to the Black Fox Mine Closure Plan, for filing. The amendment proposes expansion of the mine into the Froome Deposit, which is estimated to contain 827,000 tons of ore production. Production at Froome is planned to occur within 12 months of the project’s commencement. It is estimated that steady state production of 1500 tonnes per day will occur in the second quarter of 2021 focusing on the high grade areas of the deposit. To reach the Froome Deposit 8,500 metres of lateral development is required, this includes the 1.0 kilometer ramp from the Black Fox pit to the deposit.
Documents justificatifs
Consulter les documents en personne
Certains documents justificatifs peuvent ne pas être accessibles en ligne. Si tel est le cas, vous pouvez demander à consulter les documents en personne.
Veuillez communiquer avec le bureau mentionné ci-dessous pour savoir si les documents sont accessibles.
5520 Highway 101 E Highway
PO Box 3060
South Porcupine Ontario,
ON
P0N 1H0
Canada
Commentaire
La consultation est maintenant terminée.
Cette consultation a eu lieu 3 septembre 2020
au 3 octobre 2020
Communiquer avec nous
Contact
Andrew Persad
5520 Highway 101 East
PO Box 3060
South Porcupine,
ON
P0N 1H0
Canada
Commentaires reçus
Par l'entremise du registre
0Par courriel
0Par la poste
0