Le présent avis est fourni à titre d’information seulement. Il n’existe aucune obligation de mener une consultation sur le Registre environnemental de l’Ontario à propos de cette initiative. Pour en savoir davantage sur le processus de consultation et les types d’avis publiés sur le registre.
Pourquoi une consultation n’est pas nécessaire
On April 1, 2020, the Ontario Government made a temporary regulation to respond to the COVID-19 outbreak. Ontario Regulation 115/20 exempted all proposals for policies, acts, regulations and instruments from posting requirements under the EBR.
Ontario Regulation 115/20 was revoked on June 15, 2020, however, we are posting this decision as a bulletin because the proposal was posted on May 15, 2020 while Ontario Regulation 115/20 was in effect.
Although consultation was not required, the ministry did consult with the public on this proposal by posting ERO# 019-1789 for public comment from May 15, 2020 to June 29, 2020. To ensure transparency, the ministry is providing details of its decision and the effects of consultation on decision-making in this notice.
Détails
Proponent(s)
1. Vine Fresh Ltd.
420 Essex Road 14
Leamington, Ontario
N8H 3V8
2. Lebo Farms Ltd.
429 Mersea Road 8
Leamington, Ontario
N8H 3V8
Location details
420 Essex Road 14 and 429 Mersea Road 8
Municipality of Leamington, County of Essex
N8H 3V8
To see the site location on a map, refer to the instrument proposal under ERO# 019-1789.
Instrument decision details
Approval has been granted for the upgrade and expansion of the existing domestic wastewater treatment, servicing the two greenhouses for their workers' quarters, accessory warehouse and office facilities.
The proposed upgrade included a new moving bed biofilm reactor treatment facility with a rated capacity of 70 cubic meters per day. The existing and upgraded wastewater works will continue to discharge to Silver Creek Drain.
The approval includes monitoring of the wastewater effluent discharge leaving the site.
Comments received
No comments were received.
Effects of consultation
Third parties are not able to apply for leave to appeal in respect of proposals which were posted while Ontario Regulation 115/20 was in effect between April 1, 2020 and June 14, 2020. Ontario Regulation 115/20 exempted all proposals from instruments from posting requirements under the EBR. Leave to appeal may only be sought in respect of instruments that are required to be posted to the ERO.
Appeal information
This instrument type cannot be appealed.
Documents justificatifs
Consulter les documents en personne
Certains documents justificatifs peuvent ne pas être accessibles en ligne. Si tel est le cas, vous pouvez demander à consulter les documents en personne.
Veuillez communiquer avec le bureau mentionné ci-dessous pour savoir si les documents sont accessibles.
Communiquer avec nous
Contact
Client Services and Permissions Branch
135 St Clair Ave West
1st Floor
Toronto,
ON
M4V 1P5
Canada