October 12, 2022 - November 11, 2022 (30 days) Closed
Last updated
Permit to Take Water No. 5311-99RRDQ was renewed for Granite Golf Club on November 30, 2022 for 10 years (permit No. 7737-CKKQ2G). Water will be taken from one well for golf course irrigation purposes at the Granite Golf Club, located in the Township of Uxbridge, Ontario.
This decision is for a new Permit to Take Water for 2706913 Ontario Inc. for construction dewatering to facilitate construction at the Cedar Crescent Village development, located at 122 Elgin St., Saugeen Shores, Ontario. The permit, No. 4582-CKGU5H was issued on November 8, 2022, with an expiry date of December 31, 2023.
February 18, 2022 - April 4, 2022 (45 days) Closed
Last updated
We approved a new Environmental Compliance Approval (waste disposal site) for Lamoureux Pumping Inc. for the use and operation of a non-hazardous liquid waste transfer station located at 2251 County Road 8 in The Nation Municipality, Ontario.
November 5, 2021 - December 20, 2021 (45 days) Closed
Last updated
A new Environmental Compliance Approval (industrial sewage) was granted to Yonge Pump Limited, for stormwater management works to service proposed Gas Station development, located at 18582 Yonge Street in the Town of East Gwillimbury, Regional Municipality of York, Ontario.
We have issued an Environmental Compliance Approval (air & noise) for J.A.C. Kernohan Construction Limited, a ready-mix concrete manufacturing facility, located in the Township of Minden Hills, County of Haliburton.
August 8, 2022 - September 22, 2022 (45 days) Closed
Last updated
A new Environmental Compliance Approval was granted for the establishment of seasonal subsurface sewage disposal works, with a daily sewage flow of 2,550 litres/day, to service a cottage located at 205 Second Street, Belwood Lake, Township of Centre Wellington, Ontario.
September 7, 2022 - October 7, 2022 (30 days) Closed
Last updated
We have issued a new Permit to Take Water No. 5054-CLMP7E on December 1, 2022, with an expiry date of December 1, 2032. Water will be taken from Pond-Quarry related to dewatering, aggregate washing, dust control and manufacturing activities located in the CIty of Kingston.
October 13, 2022 - November 12, 2022 (30 days) Closed
Last updated
The Director of Exploration has made a decision on the exploration permit application PR-22-000298 to GFG Resources Inc. for early exploration activities.
The decision is to: issue the mineral exploration permit.
October 13, 2022 - November 12, 2022 (30 days) Closed
Last updated
The Director of Exploration has made a decision on the exploration permit application PR-22-000296 to RJK Explorations Ltd. for early exploration activities.
The decision is to: issue the mineral exploration permit
October 24, 2022 - November 23, 2022 (30 days) Closed
Last updated
The Director of Exploration has made a decision on the exploration permit application PR-22-000304 to Voltage Metals Inc. for early exploration activities.
The decision is to: issue the mineral exploration permit.
September 1, 2022 - October 1, 2022 (30 days) Closed
Last updated
Permit to Take Water No. 0657-C6XQC8 for Strabag Scarborough Project Inc. was amended on November 29, 2022, to increase the water taking at the site (Permit No. 1835-CLLLMU).Water will be taken from one well system for construction dewatering purposes at 4700 Sheppard Avenue East in the City of Toronto, Ontario for three years.
August 22, 2022 - October 6, 2022 (45 days) Closed
Last updated
An amended Environmental Compliance Approval was issued to GFL Environmental Inc. The amendment allows the site to accept additional waste quantities for processing; change the service area to Canada and the United States; and update the Financial Assurance.
August 16, 2022 - September 30, 2022 (45 days) Closed
Last updated
An amended Environmental Compliance Approval was issued to Norfolk Disposal Services Limited. A facility expansion is approved which will increase the site area from 1.2 hectares to 3.3 hectares, additional building construction, new weigh scale and entrance from Thompson Road.
September 7, 2022 - October 7, 2022 (30 days) Closed
Last updated
We have issued a new Permit to Take Water No. 4871-CLDJZM on November 30, 2022 to GIP Properties Corp. Water will be taken from one well related to dewatering, aggregate washing, dust control and manufacturing activities, located in the City of Cornwall. The new permit expires on November 30, 2032.
January 6, 2022 - February 20, 2022 (45 days) Closed
Last updated
A new Environmental Compliance Approval (air & noise) has been issued to 588922 Ontario Inc. for the operation of a ready-mix concrete plant, located in Haldimand County, Ontario.
February 11, 2021 - March 28, 2021 (45 days) Closed
Last updated
We have issued a new Environmental Compliance Approval to Thomas Cavanagh Construction Limited for an aggregate pit and quarry located in Lanark Highlands Township, Ontario.
October 25, 2022 - November 24, 2022 (30 days) Closed
Last updated
The Director of Exploration has made a decision on the exploration permit application PR-22-000295 to Mistango River Resources Inc. for early exploration activities.
The decision is to: issue the mineral exploration permit.
August 8, 2022 - September 7, 2022 (30 days) Closed
Last updated
The Director of Exploration has made a decision on the exploration permit application PR-22-000186 to Kenneth Fenwick for early exploration activities.
The decision is to: issue the mineral exploration permit.
October 1, 2022 - November 15, 2022 (45 days) Closed
Last updated
The Director of Exploration has made a decision on the exploration permit application PR-22-000279 to Infinite Ore Corp. for early exploration activities.
The decision is to: issue the mineral exploration permit.