We issued a new Environmental Compliance Approval (sewage) for 1108 Queen Street, in the Township of Wilmot, Ontario, for the establishment of a replacement subsurface disposal works for the collection, transmission, treatment and disposal of domestic sewage with a maximum design capacity of 15,000 litres per day.
The ministry has accepted a risk assessment prepared for the owner as part of their future development plans for a property at 545 Lake Shore Blvd. West, Toronto (southern parcel). The director is considering issuing a Certificate of Property Use.
Permit to Take Water No. 7382-DR5PZK was issued to GolfNorth Properties Inc. on February 12, 2026. Water will be taken from one pond and one well for commercial golf course irrigation purposes, located in the City of Cambridge, Ontario.
October 21, 2025 - November 20, 2025 (30 days) Closed
Last updated
Permit to Take Water No. 2731-DQ3JW2 was issued to Forterra Pipe & Precast, Ltd. on January 9, 2026. Water will be taken from two wells related to manufacturing activities in Cambridge, Regional Municipality of Waterloo, Ontario.
November 6, 2025 - December 21, 2025 (45 days) Closed
Last updated
A new Environmental Compliance Approval is granted to Aecon Kiewit Nuclear Partners for the collection, transmission, treatment and disposal of cooling water for a tunnel boring machine (TBM) and construction water at Darlington Nuclear Power Generation Station.
Permit to Take Water No. P-300-6360606337 was issued to Eden Grove Village Inc. on February 13, 2026. Water will be taken from two wells for communal water supply purposes, located in the community of Gowanstown in the town of North Perth, Ontario.
The approval is granted for a new Environmental Compliance Approval for private sewage works serving DeHaan Homes Inc., located near 26 Carter Drive, in the Town of West Lincoln.
October 29, 2025 - December 13, 2025 (45 days) Closed
Last updated
We are proposing actions to facilitate the development of a critical transmission project north of Dryden to meet anticipated growth, support critical mining projects, and improve reliability across a broad geographic area, while advancing a shared goal of reconciliation by providing economic and partnership opportunities for Indigenous communities
This proposal is for an amendment to the Environmental Compliance Approval (ECA) No. 0735-C9PMD6 for various water management ponds and collection ditches serving Greenstone Gold Mines Tailings Management Facilities located at 7921 Highway 11, in Geraldton, Municipality of Greenstone, District of Thunder Bay, Ontario.
This proposal is for an amendment to Environmental Compliance Approval No. 8368-AGGQYV for the on-site industrial wastewater treatment and disposal system serving the Ingersoll plant, located at 583278 Hamilton Road in Ingersoll, Ontario (site).
Instrument type:
Changes to the site plan for a pit or quarry
ERO number
019-8300
Notice type
Instrument
Notice stage
Decision
Decision posted
Proposal posted
Comment period
March 4, 2024 - May 3, 2024 (60 days) Closed
Last updated
Approval was granted for a site plan amendment to allow 1094490 Ontario Limited. to change the final depth of extraction in a portion of the site from above the water table to below the water table in the Township of Uxbridge.
December 12, 2025 - January 11, 2026 (30 days) Closed
Last updated
The Director of Exploration has made a decision on the exploration permit application PR-25-000262 to Barrick Gold Inc. for early exploration activities.
The decision is to issue the mineral exploration permit.
July 27, 2023 - September 10, 2023 (45 days) Closed
Last updated
Certificate of Property Use No. 5465-CRYQBU for Minto (Bank & Fifth) GP Inc., for the eastern portion of the 819 Bank Street property in the City of Ottawa was issued to owner of the property as part of their development plans for the site.
Instrument type:
Approval to amend a municipality’s official plan
ERO number
019-5079
Notice type
Instrument
Notice stage
Decision
Decision posted
Proposal posted
Comment period
June 5, 2025 - July 5, 2025 (30 days) Closed
Last updated
A decision was made on February 19, 2026 to approve Amendment No. 1 to the Northumberland County Official Plan adopted by By-law 38-2021, subject to nine (9) modifications. The approved amendment updates the official plan to add Natural Heritage System policies and mapping to the Northumberland County Official Plan.
July 25, 2025 - September 8, 2025 (45 days) Closed
Last updated
An amended Environmental Compliance Approval (air & noise) with Limited Operational Flexibility was issued to Kemira Water Solutions Canada Inc., a polyaluminium chloride and aluminum chlrohydrate manufacturing facility located in the City of Brantford, Ontario.
This proposal is for a new Environmental Compliance Approval (sewage) for the establishment of subsurface disposal works to service a residential cottage located at 198 Road 1D, Conestogo Lake, in the Township of Mapleton, County of Wellington.
This proposal is for an amendment to Environmental Compliance Approval No. 0657-AJTU6C, for Fehr Holdings Inc. for stormwater management facilities serving the phase 4 & 5 Building Expansion from the lands located at 477 Highway 77, in the Municipality of Leamington, County of Essex, Ontario.