I am a developer and the ministry review team has corrected the consultants I hire for my stormwater management jobs many times. I actually like the current process, no need to streamline anything. We usually submit our permit requests plenty in advance and know our proposals are meeting regulatory requirements once we receive our final ECA thanks to the ministry engineers and their thorough review efforts.
With this no review EASR nonsense I would subject myself to huge potential costs in case I need to make changes post construction because it turns out the works actually didn't meet design guidelines.