Lanark Lifestyles Ltd. - Environmental Compliance Approval (sewage)

La traduction française de cet avis n'est pas disponible. Nous nous excusons pour le dérangement.

Numéro du REO
019-2023
Type d'avis
Bulletin
Loi
Environmental Protection Act, R.S.O. 1990
Affiché par
Ministry of the Environment, Conservation and Parks
Date d’affichage
Dernière mise à jour

Le présent avis est fourni à titre d’information seulement. Il n’existe aucune obligation de mener une consultation sur le Registre environnemental de l’Ontario à propos de cette initiative. Pour en savoir davantage sur le processus de consultation et les types d’avis publiés sur le registre.

Résumé de l’avis

We have approved a new Environmental Compliance Approval No. 6877-BQU2LQ to Lanark Lifestyles Ltd. for the establishment of sewage works for the proposed two senior's retirement and apartment buildings, and mixed use residential/commercial retail buildings, located at 240 Gore Street East in the Town of Perth.

Pourquoi une consultation n’est pas nécessaire

On April 1, 2020, the Ontario Government made a temporary regulation to respond to the COVID-19 outbreak. Ontario Regulation 115/20 exempted all proposals for policies, acts, regulations and instruments from posting requirements under the EBR.

Ontario Regulation 115/20 was revoked on June 15, 2020, however, we are posting this decision as a bulletin as because the proposal was posted on April 2, 2020 while Ontario Regulation 115/20 was in effect.

Although consultation was not required, the ministry did consult with the public on this proposal by posting ERO# 019-1581 for public comment from April 2, 2020 - May 17, 2020. To ensure transparency, the ministry is providing details of its decision and the effects of consultation on decision-making in this notice.

Détails

Proponent(s)

Lanark Lifestyles Ltd.
240 Gore Street East
Perth, ON
K7H 1K9
Canada

Site location details

240 Gore Street East
Perth, ON
Canada

To see the site location on a map, refer to the instrument proposal under ERO# 019-1581.

Instrument decision details

Sanitary sewer and storm sewer are proposed for the development, and stormwater management works was designed to provide Enhanced Level water quality control and to attenuate post-development peak flows to 5-year pre-development flows for all storm events up to and including the 100-year storm event, discharging to the existing roadside ditch on South Street (for drainage from the north) and to the existing roadside ditch on Rideau Ferry Road (for drainage from the south), ultimately into the Tay River, consisting of the following:

  • one oil & grit separator (Hydro First Defense® Model FD-6HC or Equivalent) serving the drainage from the south (1.21 ha)
  • one oil & grit separator (Hydro First Defense® Model FD-4HC or Equivalent) serving the drainage from the north (1.0 ha)
  • quantity control with surface ponding and inlet control devices

Comments received

  • 0 received through the registry
  • 0 received by mail
  • 0 received by email

Appeal information

Appeals are not allowed.

This instrument type cannot be appealed.

Documents justificatifs

Consulter les documents en personne

Certains documents justificatifs peuvent ne pas être accessibles en ligne. Si tel est le cas, vous pouvez demander à consulter les documents en personne.

Veuillez communiquer avec le bureau mentionné ci-dessous pour savoir si les documents sont accessibles.

Communiquer avec nous

Contact

S'inscrire pour obtenir des avis

Nous vous enverrons des avis par courriel accompagnés de toute mise à jour liée à cette consultation. Vous pouvez modifier vos préférences relatives à l'avis en tout temps en allant à votre page de profil où se trouvent vos paramètres.

Suivre cet avis