Walter's Inc. requested to withdraw their application for an Environmental Compliance Approval. The application is considered withdrawn, and no approval was issued.
Instrument type:
Changes to the site plan for a pit or quarry
ERO number
026-0468
Notice type
Instrument
Notice stage
ProposalUpdated
Proposal posted
Comment period
May 13, 2026 - June 13, 2026 (31 days) Open
Last updated
Halton Crushed Stone Ltd. seeks to authorize the importation of excess soil to increase the final rehabilitation elevation by 2 meters across both licences.
Instrument type:
Changes to the site plan for a pit or quarry
ERO number
026-0471
Notice type
Instrument
Notice stage
ProposalUpdated
Proposal posted
Comment period
May 13, 2026 - June 13, 2026 (31 days) Open
Last updated
Township of East Garafraxa applied to amendapplied the current site plan for ARA Licence 625233 to extend the hours of operation of the site relating to operations on Saturdays, and extend the ability to process material on site including trucking and crushing operations.
Instrument type:
Changes to the site plan for a pit or quarry
ERO number
026-0430
Notice type
Instrument
Notice stage
ProposalUpdated
Proposal posted
Comment period
May 14, 2026 - July 14, 2026 (61 days) Open
Last updated
1712028 Ontario Inc. seeks to extract below the water table in a portion of the eastern 15 m setback, which is adjacent to land also owned by 1712028 Ontario Inc. (Port Colborne Quarries Inc.). The amendment would allow for the existing pond to be integrated with the pond proposed through the adjacent expansion application.
Instrument type:
Changes to the site plan for a pit or quarry
ERO number
026-0295
Notice type
Instrument
Notice stage
ProposalUpdated
Proposal posted
Comment period
March 31, 2026 - June 2, 2026 (63 days) Open
Last updated
Drain Bros. Excavating Limited seeks to extract below the water table in the east setbacks, which are adjacent to land also owned by Drain Bros. Excavating Limited. The amendment would allow for the existing pond to connect with the pond proposed through the adjacent expansion application.
We are proposing changes to three regulated forest manuals under the Crown Forest Sustainability Act. The Forest Management Planning Manual, the Forest Information Manual and the Scaling Manual will be revised to make forest management planning more efficient while continuing to manage Ontario’s forests sustainably.
This proposal is for a new Environmental Compliance Approval (Waste Disposal Site) to be issued to Ridgeline Farms Inc. for a processing facility located in Centre Hastings, Ontario.
September 7, 2022 - October 22, 2022 (45 days) Closed
Last updated
An Environmental Compliance Approval with the Limited Operational Flexibility (air & noise) has been granted to to Meridian Lightweight Technologies Inc., a magnesium auto parts manufacturing facility located in Strathroy-Cardoc, Ontario.
August 27, 2025 - September 26, 2025 (30 days) Closed
Last updated
The Permit to Take Water No. 7168-DTRKQH has been issued to Agnico Eagle Mines Limited on May 19, 2026, to renew the Permit No. 2625-D3GNHL. Water will be taken from one well for the purpose of mine dewatering, located in Matheson, Ontario.
August 5, 2025 - September 19, 2025 (45 days) Closed
Last updated
An amendment has been issued to Novocol Pharmaceutical of Canada, Inc. This Approval is for the renewal of the Limited Operational Flexibility for an existing Approval (air & noise) No. 6758-AL3J64, and include some additional emission sources.
The company is a pharmaceuticals manufacturing facility located in the City of Cambridge, Ontario.
This proposal is for a new Environmental Compliance Approval to construct a new septic system located at 3355 Golf Club Road, in the City of Hamilton, Ontario.
The development area will include a two-storey, 782 square metres building with guest accommodations, retreat spaces, offices and a central dining area.
This proposal is for an amendment to the Environmental Compliance Approval, ECA No. 6976 DD4KRQ for the development of an anaerobic digester and associated site infrastructure at 160 Eco Park Way, Southgate, Ontario.
July 18, 2025 - September 1, 2025 (45 days) Closed
Last updated
An Environmental Compliance Approval with operational flexibility has ben issued to CRH Canada Group Inc. operating as Ash Grove for their facility located at 2391 Lakeshore Road West in Mississauga.