The Permit to Take Water No. P-300-5274624752 was issued to A. L. Blair Construction Limited - Cinnamon Quarry on July 29, 2024, to renew the permit 3537-9EPMTV. Water will be taken from two wells and one pond on Benson George Road for dewatering and water supply purposes.
Permit to Take Water No. 5452-D4EHER was issued to GolfNorth Management Corp., operating as Rebel Creek Golf Club for 10 years. Water will be taken from one well and one pond for golf course irrigation purposes, located in Petersburg, Ontario.
The Permit to Take Water No. P-300-8262547761 was issued to Otter Creek Sand and Gravel Inc. on July 30, 2024. Water will be taken from one pond for aggregate washing purposes at the Mildmay Pit, located in South Bruce, Ontario.
November 10, 2023 - December 25, 2023 (45 days) Closed
Last updated
An amended Environmental Compliance Approval (air & noise) with Limited Operational Flexibility was issued to Freudenberg-NOK, Inc., a manufacturing facility located in Tillsonburg, Ontario.
The Director of Exploration has made a decision on the exploration permit application PR-24-000125 to Transition Metals Corp. for early exploration activities.
The decision is to issue the mineral exploration permit.
The Director of Exploration has made a decision on the exploration permit application PR-24-000139 to Shining Tree Resources Corp. for early exploration activities.
The decision is to issue the mineral exploration permit.
The Permit to Take Water No. P-300-7268907618 was issued to Construction Jadco Inc. on July 29, 2024. Water will be taken from one pond for construction dewatering purposes at 150 Laurier Avenue West, located in the City of Ottawa, Ontario.
Instrument type:
Approval for a consent (subject to conditions) in an area where there is no official plan in place
ERO number
019-8578
Notice type
Instrument
Notice stage
Decision
Decision posted
Proposal posted
Comment period
May 2, 2024 - June 1, 2024 (30 days) Closed
Last updated
Pursuant to Section 53 of the Planning Act, provisional consent for a lot severance for agricultural purposes was granted on June 19, 2024, subject to conditions.
Instrument type:
Approval for a consent (subject to conditions) in an area where there is no official plan in place
ERO number
019-8621
Notice type
Instrument
Notice stage
Decision
Decision posted
Proposal posted
Comment period
May 2, 2024 - June 1, 2024 (30 days) Closed
Last updated
Pursuant to Section 53 of the Planning Act, provisional consent for a lot severance for agricultural purposes was granted on June 19, 2024, subject to conditions.
The Director of Exploration has made a decision on the exploration permit application PR-24-000077 Vanguard 2024 project to Thunder Gold Corporation for early exploration activities.
The decision is to issue the mineral exploration permit.
On July 26, 2024, the Minister of Municipal Affairs and Housing filed a Minister’s Zoning Order with the Registrar of Regulations as Ontario Regulation 304/24 in the City of Barrie. The Zoning Order was requested by the Minister of Long-Term Care to accelerate the development of a long-term care (LTC) facility.
Permit to Take Water No. 6420-D78VJ9 was issued to Carrying Place Golf and Country Club on July 22, 2024, to renew Permit to Take Water No. 8060-BDYKLU for golf course irrigation purposes. Water will be taken from one irrigation pond in the Township of King, Regional Municipality of York, Ontario for 5 years.
New Permit to Take Water No. P-300-5279477438 was issued to Tribute (King Street) Limited on July 23, 2024, for construction dewatering purposes. Water will be taken from three ponds in the Town of Courtice, Municipality of Clarington, Ontario for 6 years.
Permit to Take Water No. 5228-D78UYP was issued to Camp Tamarack Ltd. on July 19, 2024, to renew Permit to Take Water No. 8000-9GGRLD for campground water supply purposes. Water will be taken from three wells in the Town of Bracebridge, District Municipality of Muskoka, Ontario for 10 years.
November 29, 2023 - January 13, 2024 (45 days) Closed
Last updated
We have issued a new multi-site Environmental Compliance Approval (geothermal) for HAMMER RIG RENTALS (CANADA) INC. and UNDERCITY ENERGY INC. to install vertical closed loop ground source heat pumps throughout Ontario.
October 25, 2023 - December 9, 2023 (45 days) Closed
Last updated
We have issued a new multi-site Environmental Compliance Approval (geothermal) for 2068929 Ontario Inc., operating as Buchanan & Hall, to install vertical closed loop geothermal systems. Buchanan & Hall operates across Ontario drilling boreholes and installing closed loop geothermal heat exchangers in these boreholes.
Instrument type:
Approval for a consent (subject to conditions) in an area where there is no official plan in place
ERO number
019-7693
Notice type
Instrument
Notice stage
Decision
Decision posted
Proposal posted
Comment period
October 4, 2023 - November 3, 2023 (30 days) Closed
Last updated
Application 60-C-234706 was approved on July 25, 2024 subject to conditions. The last date to appeal the decision under the Planning Act is August 14, 2024.